Hindustan Times (Noida)

Bharatmala project hit by delays, shortage of funds

HIGHWAYS Ambitious project may be set back by issues, including land acquisitio­n delay

- Anisha Dutta letters@hindustant­imes.com

NEWDELHI: Prime Minister Narendra Modi’s ambitious ₹5.35 lakh crore Bharatmala Pariyojana, an umbrella project launched in 2017 and hailed as India’s biggest highways developmen­t plan, is beset by delays at multiple implementa­tion stages amid funding shortages, according to a central government report reviewing its progress until September.

According to the report, a copy of which has been reviewed by Hindustan Times, project implementa­tion under the programme could also be set back by delays in land acquisitio­n, detailed project report (DPR) preparatio­n, the bidding process, appointmen­t of concession­aires and physical constructi­on.

“Projects implemente­d under Bharatmala Pariyojana could potentiall­y be delayed during multiple stages across the project lifecycle,” said the National Highways Authority of India (NHAI) report.

The first phase under the project has an estimated investment outlay of ₹5.35 lakh crore according to the investment plan approved by the Cabinet Committee on Economic Affairs (CCEA), spanning a period of five years (from FY 2017-18 to FY 2021-22).

The mammoth project is aimed at bridging critical infrastruc­ture gaps through the developmen­t of economic corridors, so-called inter- corridors and feeder routes, border and internatio­nal connectivi­ty roads, coastal and port connectivi­ty roads and greenfield expressway­s.

A total of around 24,800 km are being considered for constructi­on in Phase I of the project. In addition, it also includes 10,000 km of work remaining under the National Highways Developmen­t Project (NHDP), an older initiative.

“Considerin­g the massive scale of the program, it is extremely important to manage the implementa­tion of the program and monitor its physical and financial progress through a robust Program Management Office (PMO). AT Kearny and CRISIL were appointed as the program management consultant­s (PMCS) to support...managing the implementa­tion of Phase 1,” the report said.

Different components of the project will be implemente­d by the ministry of road transport and highways (MORTH) through various agencies -- NHAI, National Highways and Infrastruc­ture Developmen­t Corporatio­n Limited (NHIDCL) and state Public Works Department­s (PWDS) and state Road Developmen­t Corporatio­ns (RDCS).

FINANCIAL WOES

The report has noted that the total capital cost for the awarded projects exceeds the cost approved by the CCEA by 50%. The capital cost of 6,361 KM of projects awarded under Bharatmala is ₹1.475 lakh crore.

Of this 4383 km of projects worth ₹1.03 lakh crore are those that have been awarded afresh, with the remaining coming from existing and incomplete NHDP projects.

“The capital cost for awarded projects is ₹23.1 crore per km... The total awarded cost exceeds the cost approved by CCEA by 50% ie ₹15.5 crore per km,” the report said, referring to the projects awarded afresh.

For Bharatmala projects, the proportion­ate increase in awarded cost over the approved cost is higher for the cost of land acquisitio­n than the civil cost. The latter was 17.3 crore per km as opposed to an approved ₹13.7 crore per km, and the former ₹ 6.2 crore as opposed to a mere ₹1.8 crore, which turned out to be 3.4 times higher, according to the report.

The total awarded capital cost for NHDP projects also exceeds the cost approved by CCEA by 50%.

“Thus, the programme is running significan­tly behind its financial targets. This is likely to lead to more stringent award targets for the remaining part of the year,” the report said.

LAGGING IN OTHER TARGETS

Projects with a total length of 8,134 km were targeted to be awarded by NHAI in the current financial year, of which only 268 km had been awarded till September 2018.

“Out of the 321 km that was targeted to be awarded in the first quarter 118 km have been awarded in the same period. Out of the revised award target of 2,707 km of projects for the second quarter only three projects with a length of 150 km have been awarded till September 2018...,” the report noted.

Of 122 projects with a total length of 5,944 km targeted to be awarded till January 2018, bid documents have not been submitted for 58 projects of 3,209 KM.

Jaijit Bhattachar­ya, president at the Centre for Digital Economy Policy Research, said, “The purpose of the report is to analyse where the issues are... but there has been a huge improvemen­t from what was happening 10 years ago...”

Newspapers in English

Newspapers from India