Hindustan Times (Noida)

Kathputli Colony revamp set to miss March 2019 deadline

- Risha Chitlangia risha.chitlangia@htlive.com

NEW DELHI: Delhi Developmen­t Authority’s much-delayed Kathputli Colony in-situ redevelopm­ent project is likely to miss its March 2019 deadline.

According to DDA officials, while constructi­on has started, a few hurdles remain — including a delay in providing electricit­y at the constructi­on site.

Speaking at an event last week, Union housing and urban affairs minister Hardeep Singh Puri had said DDA would start relocating slum dwellers by March 2019. But DDA officials cite technical hurdles for the slow pace of work.

Puri had said: “If you have to resettle people (slum dwellers), it has to be on ‘as is, where is’ basis. I’m happy to inform you that in Kathputli Colony…by March 2019 we will be able to relocate those 2,800 families (who are living in transit camps) in where they lived earlier to modern, green, resilient buildings.”

Authority officials say efforts were on to get some units ready by March next year. They say one of the main hurdles is providing electricit­y at the constructi­on site as Tata Powers-delhi Distributi­on Limited (Tata Power-ddl), the discom in the area, refused to give a connection to the developer (Raheja Developers). “The discom is not giving electricit­y citing pending dues of slum dwellers. DDA has nothing to do with it. But the discom is refusing to give electricit­y at the constructi­on site. It is difficult to work without an electricit­y connection. We have raised the matter with the discom,” said a senior DDA official aware of the developmen­t.

A Tata Power-ddl spokespers­on said, “Tata Power-ddl has been supplying power to Katputli Colony since 2010 but we have been facing challenges in recovering bills from the consumers. The pending bills have now mounted to ₹3.25 crore. As per DERC Supply Code Regulation, in case of reconstruc­tion of existing property, supply will be given to the owner /occupier /developer of the premises only after clearance of outstandin­g dues.tata Power-ddl is only following the guidelines of DERC.”.

A spokespers­on of Raheja Developers said: “We are trying our level best as work is going on 24x7. Power connection from NDPL and final boundary with railways is being formalised.”

Another hurdle is a small piece of land measuring 2,500 sqm on a 5.2 hectares disputed area. “But this portion is not located where the residentia­l complex is to be constructe­d,” said a DDA official.

DDA officials say constructi­on of residentia­l components has started and efforts are underway to complete some units by March 2019. “We have been holding regular meetings with the developer. By March, we hope some units will be ready,” the official said.

Raheja Developers awarded the contract for in-situ redevelopm­ent

2,641 families found eligible in the initial survey

Locals challenge DDA’S survey in the Delhi high court

Some slum dwellers shift to transit camp in Anand Parbat

DDA starts eviction and demolition drive in December

DDA adopts DUSIB’S policy for slum rehabilita­tion and extends the cut-off date to January 1, 2015; fresh survey carried out in which 3,292 people found eligible

Union minister Hardeep Singh Puri lays foundation stone for the project, says dwellers will be able to relocate by March

Newspapers in English

Newspapers from India