Besides the Ram temple, several infrastruc­ture projects promise to change the face of the pilgrim town

-

➘ RAM TEMPLE

Budget: `1,800 crore

Deadline: Constructi­on of ground floor should get completed three months before December 2023. Darshan will begin after installing the Ramlalla idol in the sanctum sanctorum. The full temple should be ready by 2025

Status: Constructi­on on in full swing

➘ MARYADA PURUSHOTTA­M SHRIRAM AIRPORT

Budget: `525 crore Deadline: Air strip to be finished by December 2022, Terminal 1 by March 2023 Status: Phase 1 progressin­g fast

➘ RAILWAY STATION

Budget: `350 crore Deadline: First phase to be finished by December 2022

Status: Phase 1 is expected to be functional by the end of this year

➘ NAVYA AYODHYA, 1,500-ACRE VASTU-FRIENDLY TOWNSHIP

Budget: `10,000 crore

Deadline: Final vision to be completed by 2047 Status: At various stages of constructi­on

➘ THREE NEW PATHS TO THE RAM TEMPLE

Budget: `1,000 crore

Deadline: Between March 2023 and December 2023

Status: At various stages of completion

➘ A 67 KM-LONG RING ROAD TO CONNECT AYODHYA WITH OTHER TOWNS

Budget: `500 crore

Deadline: Land acquisitio­n to be completed by January 2023 Status: Work yet to start

➘ LUXURY CRUISE SERVICE ON SARAYU RIVER

Budget: Not revealed

Deadline: End of 2022 Status: Almost ready to operate

➘ FOUR SHOPPING AND PARKING COMPLEXES

Budget: `100 crore

Deadline: December 2023 Status: At different stages of constructi­on

➘ LATA MANGESHKAR SMRITI CHOWK

Budget: `7.9 crore Deadline: September 2022 Status: Almost completed

➘ THE MOSQUE

Budget: `100 crore

Deadline: Not fixed yet Status: Land allotted but constructi­on not permitted yet because the fire deparment has denied an NOC *All budget figures are tentative

 ?? ??
 ?? ??
 ?? ??
 ?? ??