Millennium Post (Kolkata)

425 infra projects hit by cost overruns of over `4.83 lakh cr

- OUR CORRESPOND­ENT

NEW DELHI: As many as 425 infrastruc­ture projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.83 lakh crore, according to a report.

According to the Ministry of Statistics and Programme Implementa­tion, which monitors infrastruc­ture projects of Rs 150 crore and above, out of 1,579 projects, 425 projects reported cost overruns and as many as 664 projects were delayed.

“Total original cost of implementa­tion of the 1,579 projects was Rs 21,95,196.72 crore and their anticipate­d completion cost is likely to be Rs 26,78,365.62 crore, which reflects overall cost overruns of Rs 4,83,168.90 crore (22.01 per cent of the original cost),” the ministry’s latest report for March 2022 said.

According to the report, the expenditur­e incurred on these projects till March 2022 stood at Rs 13,88,760.73 crore, which is 51.85 per cent of the anticipate­d cost of the projects.

However, the number of delayed projects decreased to 561, if delay is calculated on the basis of the latest schedule of completion.

Further, for 606 projects nei

‘Total original cost of implementa­tion of the 1,579 projects was Rs 21,95,196.72 crore and their anticipate­d completion cost is likely to be Rs 26,78,365.62 crore’

ther the year of commission­ing nor the tentative gestation period has been reported.

Out of the 664 delayed projects, 94 have overall delays in the range of 1-12 months, 124 have been delayed for 13-24 months, 331 projects for 25-60 months and 115 projects have been delayed for 61 months and above. The average time overrun in these 664 delayed projects was 42.41 months.

Reasons for time overruns as reported by various project implementi­ng agencies include delay in land acquisitio­n, delay in obtaining forest and environmen­t clearances, and lack of infrastruc­ture support and linkages.

Delay in tie-up for project financing, delay in finalisati­on of detailed engineerin­g, change in scope, delay in tendering, ordering and equipment supply, and law and order problems are among the other reasons.

The report also cited statewise lockdowns due to COVID19 as a reason for the delay in implementa­tion of these projects. It has also been observed that project agencies are not reporting revised cost estimates and commission­ing schedules for many projects, which suggests that time/cost overrun figures are under-reported, it stated.

 ?? ??

Newspapers in English

Newspapers from India