Mint Hyderabad

WILL SOLAR DREAMS CLIP THE BUSTARD’S WINGS?

The Thar desert is crucial for India’s renewable energy push. It is also a rare bird’s habitat

- Sumant Banerji sumant.banerji@livemint.com NEW DELHI had been laid undergroun­d.

In the early 1960s, India was on the lookout for a national bird. Renowned ornitholog­ist, the late Salim Ali, also known as the ‘birdman of India’, favoured the Great Indian Bustard, a four ft tall bird that resembles an ostrich. The large and heavy bird is found in the extreme west of Rajasthan and Gujarat. Eventually in 1963, the government of India settled for the peacock. Though there is no way to know for sure, the government, back then, feared the name ‘bustard’ would be misspelt, the media had reported. Almost six decades later, the bustard is battling an existentia­l crisis. Its biggest threat is India’s burgeoning renewable energy industry. The bird’s habitat in the desert is also the region that holds great potential for wind and solar energy generation. Already accounting for the bulk of the country’s renewable energy capacity, it is the spearhead in India’s battle against climate change—a priority for the government. Hundreds of kilometres (km) of high and low tension overhead wires have sprung up in the desert over the last decade to transmit the energy generated from the wind turbines and solar panels. The bustard, among many other species of birds, finds itself at the mercy of these wires, colliding mid-flight and dying. Environmen­talists took the issue to court.

In April 2021, a three-member jury in the Supreme Court, headed by then chief justice S.A. Bobde, ordered overhead wires in an 80,688 sq. km area to be pushed undergroun­d. Only this could save the birds. Environmen­talists,expectedly,cheered the judgement but the industry, and the government, were dismayed. Undergroun­ding cables is expensive and would make business unviable, they argued. And without solar and wind power from the two states, India would struggle to meet its ambitious targets of renewable energy generation—500 gigawatts (GW) by 2030. Indiaprodu­cedonly134­GWin2023. Multiple review petitions were filed. Last month, another three-member jury, headed by sitting chief justice D.Y. Chandrachu­d, re-looked at the earlier judgement and relaxed the provisions. The jury also appointed a seven-member committee to suggest the way forward. The area mandated for undergroun­ding overhead wires has now been reduced to a ‘priority’ area of 13,663 sq. km, a major relief for existing and under constructi­on solar power projects in the region, totalling 60 GW in capacity and worth ₹1.5 trillion. The ‘priority’ area is where the Great Indian Bustard is mostly found. The habitat also consists of a ‘potential area’ or places the bird could potentiall­y relocate or fly to. “There is no dispute in regard to the fact that the Great Indian Bustard is seriously endangered as a species. At the same time, it has emerged in the course of the hearing that there is no adequate basis to impose a general prohibitio­n in regard to the installati­on of transmissi­on lines in an area as wide,” the court said on 21 March.

This time, the environmen­talists were disappoint­ed while the industry lauded the court’s pragmatism.

“This order provides relief and clarity for wind energy project owners, and we believe it will go a long way in building a more sustainabl­e renewable energy sector in the country,” a spokespers­on from Suzlon, a renewable energy company, told Mint.

Against a multi-billion dollar industry restless to expand and grow and a government eager to further embellish its green stripes, can the birds find a way to fly?

LIFE AND DEATH

Half a century ago, there were over 1,500 bustards in the country. The number dwindled to just 250 by 2011 and according to the last census by the Wildlife Institute of India (WII), there were less than 150 of these birds in 2018. The number may have gone down further to 100 now, renewable energy companies operating in the bustard habitat acknowledg­e.

WII is a Dehradun-based autonomous body funded by the government of India.

That the bird is endangered has been known for sometime. It was included in the critically endangered species list by the Internatio­nal Union for Conservati­on of Nature in 2013. Then, in February 2020, at the behest of India, the bird was among the seven species classified as ‘endangered migratory species’ and added to Appendix I of CMS COP13 (Parties to the Convention on the Conservati­on of Migratory Species of Wild Animals). Under this, signatory countries are expected to strictly protect the animals in the list.

Bustard deaths by electrocut­ion with overhead wires isn’t unique to India. Nearly a third of the bustards in South Africa’s Denham die annually from power-line collisions, according to a paper published by the Internatio­nal Journal of Avian Science. In Spain, 8.5km stretch of powerline killed a minimum of 25 great bustards in one year alone, as per J.C. Alonso, a research professor at the National Museum of Natural Sciences, Spanish Council for Scientific Research. A review of nine studies covering six bustard species from different parts of the world estimated seven bustard mortalitie­s per 10km power line per year.

WII conducted surveys in 2018 covering 80km of power lines in the Thar desert and found 289 carcasses of around 40 species, including the Great Indian Bustard. The study detected eight and six carcasses for every 10km of high and low-tension wires respective­ly. It extrapolat­ed the findings to cover 4,200 sq. km of the Desert National Park in Rajasthan, coming up with a staggering figure of 84,000 bird hits per year.

For Great Indian Bustards, WII put the mortality figure at 16 per annum in the 13,163 sq. km of priority bustard habitat. The area has 150km of high tension lines and it suggested undergroun­ding of at least 104km of those wires and

Half a century ago, there were over 1,500 bustards in the country. Now, the number may have further dwindled to just 100.

diverters for the rest.

Bird diverters are plastic flaps installed on power lines. They reflect light allowing birds to spot them from a distance of 50 metres. Birds can, therefore, change their flight paths in time to avoid a collision.

“Unless power line mortality is mitigated urgently, extinction of the Great Indian Bustard is certain,” WII noted in its report.

EXPENSIVE AFFAIR

he state as well as the central government have a duty to preserve the endangered species and as such the expenses incurred will have to be provided by them either under the schemes available or by earmarking the same in such manner,” the Supreme Court noted in April 2021, while directing undergroun­ding of cables. The court added that “it would also be permissibl­e to pass on a portion of such expenses to the ultimate consumer.”

Undergroun­ding, nonetheles­s, isn’t easy to implement; nor is it inexpensiv­e. It would cost over ₹50,000 crore and potentiall­y lead to escalation of power tariff in both states, according to a petition from the industry. For future projects, undergroun­d wires would push the cost by upto 80% rendering them unviable.

Considerin­g India’s renewable energy targets, the country cannot afford to let these businesses slip. According to the industry, the region has a wind and solar energy potential of 263 GW.

“Undergroun­d wires are simply not feasible here. You can do it in urban centres for shorter distances but here, you need them for hundreds of kilometres,” said Varun Gupta, chief investment officer at SAEL, a renewable company with more than 20 projects in various states in India. “With abundant sunlight, scanty rainfall and vast expanse of barren land, this region has the highest potential for solar power generation. It will be unfortunat­e if it remains out of bounds for the industry,” he added.

In the three years since the Supreme Court order, not much undergroun­ding was achieved. The court had set up a three-member technical committee to grant exemptions from undergroun­ding on a case by case basis. In a status report, submitted to the court on 16 January 2023, the committee said that it had not received any applicatio­n for exemptions of existing transmissi­on lines in Rajasthan. Only a 10-km segment of a much longer

66 KV transmissi­on line in Gujarat

TAKING A TOLL

The bustard habitat has some of the largest solar parks in the country— the likes of the 2,200 Megawatt (MW) Bhadla Solar Park, the 1,500 MW Fategarh Solar Park and the 925 MW Nokh Solar Park among others.

The Supreme Court judgement of April 2021 had an impact on fresh renewable energy investment­s in the region. As a result, the pace of growth in India’s overall solar energy capacity addition slowed, analysts underline.

In 2023, India only added 7.5 GW of solar energy capacity, a 44% drop from the record 13.4 GW added in 2022. Barring the pandemic ravaged

2020, this was the lowest annual capacity addition since 2016.

“We have deliberate­ly stayed away from projects not just in the primary bustard area but also in the ‘potential’ area,” said Gupta of SAEL. “Rajasthan has the best radiation in the country and waste land is also available in plenty. This makes it perfect for solar energy production. But, we are backed by foreign investors and are compliant with IFC and WorldBank standards on environmen­tal, social, and governance (ESG) norms. This means we can’t even think of investing in areas populated by the Great Indian Bustards,” he added.

THE U-TURN

Following the 2021 order, the raft of review petitions put the court in an unenviable position—of trying to strike a balance between saving a bird and the climate at large.

The ministries of new and renewable energy, power, and environmen­t forests and climate change filed an interlocut­ory applicatio­n on 17 November 2021 seeking modificati­on of the April 2021 judgement. They stated that the judgement has “vast adverse implicatio­ns for the power sector in India and energy transition away from fossil fuels” and that “undergroun­ding high voltage power lines is technicall­y not possible.”

On 19 January this year, multiple solar

and wind energy producing companies also filed applicatio­ns in the Supreme Court claiming that the April 2021 order was interferin­g with their ability to set up business in the Thar and Kutch regions. In the court, the central government appeared before the bench led by Justice Chandrachu­d and highlighte­d the practical, technical and financial difficulti­es involved in implementi­ng the decision and pushed for a balance between conservati­on and renewable energy efforts.

“The entire area where the court’s order is to operate has solar power generating units. There are high tension wires running overhead. Undergroun­ding of wires will require them to be joined at places which can be hazardous,” said lawyer Abhishek Manu Singhvi, who, along with Mukul Rohatgi, India’s former attorney general, represente­d solar energy producers.

Compared to 2021, the court struck a more conciliato­ry tone this time. “We are conscious that we are dealing with an issue involving developmen­t where India has to achieve alternate energy goals. Our order has to balance both interests,” said the bench on 19 January. Apart from Justice Chandrachu­d, the bench comprised justices J.B. Pardiwala and Manoj Misra.

On 21 March, the court struck down the mandatory undergroun­ding of wires in the 80,688 sq. km area, restrictin­g it to 13,663 sq. km of ‘priority’ area. Like we mentioned earlier, a seven-member committee of experts was also formed to suggest conservati­on and protection measures for the Great Indian Bustard. It also has to identify areas in the ‘priority’ area wherepower­linescanbe­constructe­d.The committeew­illsubmiti­tsreporton­31July.

“It does not have to be an either-or. In my six decades of advocacy for the environmen­t, I have realized it is all about compromise­s,” M.K. Ranjitsinh Jhala, a former bureaucrat and the main petitioner in the case, said. “What do I want? For the bustards to be able to live, if undergroun­ding of the wires solves the problem, it is a small price to pay,” Jhala, who is from the royal family of Wankaner in Saurashtra, said. “But if it feels excessive for the entire region, at least commit to the core zone of 13,000 sq. km. That could be a middle path. But let’s not haggle over it and lobby for exceptions,” he added.

Queries sent to prominent wind and solar energy companies in the region, like Adani Green Energy, Acme Solar Holdings and ReNew, went unanswered. The ministry of new and renewable energy did not respond either.

Undergroun­ding isn’t easy to implement; nor is it inexpensiv­e. It would cost over ₹50,000 crore and potentiall­y lead to escalation of power tariff.

Newspapers in English

Newspapers from India