Cost overrun of Rs 1.71L cr in infra projects

-

As many as 322 infrastruc­ture projects worth Rs 150 crore or above each have seen cost overrun of Rs 1.71 lakh crore due to delays and other reasons by March 2017, according to a report. "Total original cost of implementa­tion of the 1,231 projects was Rs 15,59,571.06 crore and their anticipate­d completion cost is likely to be Rs 17,31,162.47 crore, which reflects overall cost overruns of Rs 1,71,591.41 crore (11 per cent of original cost)," a flash report by the Ministry of Statistics and Programme Implementa­tion (MoSPI) said.

Out of 1,231 projects, a total 322 projects reported cost overrun, the report said. The flash report provides details on the status of the 1,231 central infrastruc­ture projects that cost Rs 150 crore and above. In March, 2017, out of 1,231 projects, nine were ahead of schedule, 324 were on schedule, 327 were delayed and 322 projects showed cost overrun. The report said that 105 projects showed both time and cost overrun with respect to original implementa­tion schedules. The number of delayed projects decreases to 233 if delay is calculated with reference to latest revised schedule of completion, the report said.

It stated that out of 327 delayed projects, 63 projects have overall delay in the range of 1 to 12 months, 67 projects have delay in the range of 13 to 24 months, 119 projects have delay in the range of 25 to 60 months and 78 projects have delay of 61 months and above. The report stated that the expenditur­e incurred on these projects till March 2017 is Rs 7,46,480.94 crore, which is 43.12 per cent of the anticipate­d cost of the projects. According to report, there were 311 projects showing time overrun.

Newspapers in English

Newspapers from India