Traffic diversions for girder launching of Kopri bridge
Thane traffic department announced diversions for the construction of Kopri Railway Bridge. The girder launching is scheduled on January 16, 17 and 18, leading to traffic diversions. The construction of Kopri Railway Bridge has been carried by MMRDA.
Hence, the launching of the girder has been schedule, between 11pm on, January 16, which will continued till 6am, on January 17. While, the same time schedule between January 17 and 18, will be followed to carry the launching process.