The Free Press Journal

Over 1k illegal structures razed along W Rly tracks

The drive is being deemed fearless as the rlys didn't change course fearing political interventi­on

- SHASHANK RAO shashank.rao@fpj.co.in

In a massive anti-encroachme­nt drive, the Western Railway has removed as many as 1,642 encroachme­nts in the last two years after carrying out 94 demolition drives on both sides of the rail tracks and rail land. These illegal structures were part of 11,517 encroachme­nts, including 6,209 encroacher­s along the Churchgate-Virar stretch and the remaining 5,308 inside the railway colonies.

The railway officials agreed that never before have they been so aggressive in removing unauthoris­ed settlement­s from railway land in the last so many years now. Last year, the Supreme Court slammed the Indian Railways for not taking action against unauthoris­ed settlement­s.

The drive will serve as a booster for the 5 and 6 rail lines on Mumbai CentralBor­ivali stretch, which has been lagging since 2008. Sources said that in April out of the 600 plus encroachme­nts identified for this Rs 930 crore project, they have provided rehabilita­tion to around 230 or so. This comes at a time when encroacher­s also came up to the WR authoritie­s demanding rehabilita­tion in the same locality from where they are being removed.

“In the last two financial years, a total 94 demolition drives were carried out with removal of a total 1,642 encroachme­nts. In the current financial year, 10 demolition drives have already been carried out with the removal of a total 564 encroachme­nts,” apprised a senior WR official on condition of anonymity.

In the year 2020-21, the WR authoritie­s removed 604 encroachme­nts by undertakin­g 32 demolition drives. The number of demolition drives almost doubled with 62 being carried out from which they managed to remove 1,038 encroacher­s in 2021-22. The railways categorize encroachme­nts as ‘soft’ and ‘hard’ wherein it depends on the structure.

In February this year, the WR decided to acquire 444 sq meters of land in Vile Parle and Borivali after demolishin­g more than 10-12 structures. Sources said that despite demolition being carried out, work got delayed but earlier last week they finally started the process for carrying out earthwork on BorivaliKh­ar stretch for the sixth line.

These proposed lines are part of the Mumbai Urban Transport Project (MUTP2) that was proposed way back in 2008-09 or so when initial cost was Rs 430 crore. The rehabilita­tion and resettleme­nt of land holders shall be done through Mumbai Metropolit­an Region Developmen­t

Authority. The slum dwellers residing in these unauthoriz­ed structures claim that they were given only seven days to vacate.

The 5-6 lines on Mumbai Central-Borivali stretch are meant to segregate the long distance trains from suburban trains. The 5th line is partially laid between Santacruz-Borivali and Mumbai CentralMah­im stretches and work on the remaining portion is underway.

Due to encroachme­nt, the works of proposed Lines 5,6 had been lagging since 2008

 ?? ??

Newspapers in English

Newspapers from India