Smart City contractor­s, workers still out of ‘site’

- THE GOAN I

More than 72 hours after the disruption caused by last Saturday’s deluge, sites either dug or cordoned-off in the capital city for smart city work, are yet to return to normalcy and wore a deserted look throughout Tuesday.

Currently, in areas where the work of constructi­ng the sewerage chamber network is completed, the contractor­s are working on providing connection­s to the buildings and houses but on Tuesday the work had not picked up pace.

As reported earlier, the rains and flooding witnessed last Saturday morning had damaged the redesigned pavements, including washing away of the freshly laid interlocki­ng tiles. There was no activity even to restore these damaged portions of pavements in several areas of Panaji until late Tuesday evening.

Another area where worker movement and activity was slack on Tuesday is the area at the Taj Vivanta junction at St Inez where according to one of the supervisor­s, the ‘smart

road’ work is in the home stretch for a section from there right up to the PWD office at Tonca.

The supervisor admitted that water-logging and softening of the soil due to the rain had made working there impossible and a couple of days more of dry weather may be necessary to normalise their pace.

The wet soil has also brought to a halt work related to laying of undergroun­d cables, including optical fibre cables, of the many service providers. In several areas the damage done by Saturday’s deluge is yet to be undone so that work can restart.

Meanwhile, the flooding on Saturday has served as a wake-up call for government authoritie­s, the Corporatio­n of City of Panaji as well as officials of Imagine Panaji Smart City Private Ltd (IPSCDL) to pay attention to servicing the existing undergroun­d, storm-water drainage system of the city.