NTPC’s installed capacity at 55,126 MW

-

Public Sector power generator NTPC announced the increase of its total installed capacity to 55,126 MW with the commission­ing of the first unit of 800 MW of Gadarwara Super Thermal Power Project (2x800 MW). The Gadarwara Supercriti­cal coal-based power project is located in Madhya Pradesh. In a statement issued here on Monday, the company said itaims to achieve a total installed capacity of 130 GW by 2032.