Electricit­y consumers in urban areas pay higher developmen­t charges

-

Electricit­y consumers applying for a new service connection in Coimbatore city or any other urban area in the State are being charged higher developmen­t charge for the last few days.

For instance, if the developmen­t charge for a single phase connection was ₹ 5,192 about a month ago, it is ₹ 9,487 now. Similarly, for a three phase connection, the charges have increased from ₹ 12, 717 to ₹ 21, 912 per new connection. This is the case for domestic connection­s too.

An electricit­y consultant in Coimbatore said that if the deposit amount was increased, the consumer would get it back. But, the hike is in developmen­t charges and it is a steep increase. Consumers get to know about it only when they submit an applicatio­n for a new connection.

An official of the Tamil Nadu Generation and Distributi­on Corporatio­n (Tangedco) said the problem was due to a technical glitch and it would be set right in a week or so. For consumers who are paying higher charges till then, the additional amount will be refunded.

“We are combining the softwares and so for any urban area, the system is collecting the developmen­t charges for undergroun­d electricit­y cables, even if the area does not have the undergroun­d power cables. This issue was taken up with the head office and it will be set right,” the official said.

A. D. Thirumoort­hi, technical advisor to the Indian Wind Power Associatio­n, said the Tangedco has to get the approval from the Tamil Nadu Electricit­y Regulatory Commission to collect higher developmen­t charges.

However, areas covered with undergroun­d cable need to be mapped properly across the State. Small areas where undergroun­d cable was laid for one or two connection­s cannot be taken as undergroun­d cable covered place. A large area should be brought under UG cable. This is an issue that was taken up with the Tangedco earlier too, he said.