Fund paucity, technical hassles hit Mullassery canal restoratio­n work

Flooding caused by pipe bursts has delayed work. Trenches dug for constructi­on getting flooded by wastewater from pipes laid by KWA

-

Paucity of funds and technical hassles are delaying the Mullassery canal restoratio­n work even as the project is delayed by over two years.

Though the authoritie­s had earlier waited for the monsoon showers to be over to resume work, flooding caused by pipe bursts is at present delaying the process.

The trenches dug for the constructi­on of the canal are getting flooded by wastewater from pipes laid by the Kerala Water Authority (KWA).

Canal work near Fashion Street and the KSRTC bus station was hit by flooding. Workers are finding it difficult to pump out water and resume work, said K.S. Bijili, the contractor of the Public Works department (PWD), who is executing the work.

The schedule of the work has been disrupted owing to the delay in clearing water that got accumulate­d in the trenches. The restoratio­n work, which began in the morning hours during the last few days, ended in the early hours of the following day, he said. Meanwhile, the delay in clearing project bills due to financial constraint­s has added to the worries of the authoritie­s. The State owes the contractor around ₹2.5 crore for the work completed so far. The payment of bills was getting delayed, which was a cause of concern, said Mr. Bijili.

The district authoritie­s have fixed May 31 as the deadline for the urban flood mitigation project, which is implemente­d in the city as part of Operation Breakthrou­gh. The Kerala High Court is actively monitoring the project.

The authoritie­s could complete only 350 metres of the 829metrelo­ng canal so far. At present, the work is being carried out simultaneo­usly on two stretches — one on MG Road and the other near the KSRTC bus stand. However, the work in one more reach has to be done simultaneo­usly to meet the May 31 deadline. Preparatio­ns are on to begin the work on Chittoor Road, said a PWD official who is involved in the implementa­tion of the project.

The delay in clearing bills owing to financial exigencies may reflect on the proposal to begin the work in the third reach of the canal. More workers and equipment need to be brought in for the process, he added.

 ?? THULASI KAKKAT ?? The schedule of the Mullassery canal restoratio­n work has been disrupted due to delay in clearing water that got accumulate­d in the trenches.
THULASI KAKKAT The schedule of the Mullassery canal restoratio­n work has been disrupted due to delay in clearing water that got accumulate­d in the trenches.