Long delays plague hydel projects of KSEB

60-MW Pallivasal Extension Scheme, 40-MW Thottiyar scheme, 24-MW Bhoothatha­nkettu project have overshot their deadlines by several years

-

Long delays have hit the commission­ing of a clutch of hydroelect­ric projects which could have helped Kerala tackle the soaring demand for electricit­y this summer.

Topping this list are the 60-megawatt (MW) Pallivasal Extension Scheme and the 40-MW Thottiyar scheme in Idukki district and the 24-MW Bhoothatha­nkettu project in Ernakulam district, all of which have overshot their deadlines by several years. Although work on these projects has entered the ˆnal stages, administra­tive issues are holding back their completion, sources said.

At a meeting with Electricit­y Minister K. Krishnanku­tty on Wednesday, KSEB unions had sought urgent steps to get the projects commission­ed at the earliest.

Since 2007

The Pallivasal Extension Scheme has been on the KSEB wish list since 2007 when work was initially awarded to the ESSARDEC-CPPL consortium. Under that agreement, the project should have been commission­ed in 2011. But the contract was terminated in 2018 following problems related to machinery, geological issues, and personnel.

A new contractor was hired to complete the installati­on of machinery, but delays continued to haunt this project. As per the latest KSEB update, 86.28% of the work on the ₹459.61-crore project is over.

The KSEB had accorded administra­tive sanction for constructi­ng the Bhoothatha­nkettu project in October 2013 at a cost of ₹231.21 crore. Civil works kicked o™ in 2014 and electromec­hanical works the following year.

Original deadline

The original deadline set for commission­ing this project was February 14, 2016. As per the latest updates from the KSEB, 98.52% of the work has been completed.

In 2022, Mr. Krishnanku­tty had listed these two projects among four hydel projects that were due for commission­ing that year, but that did not happen.

Another project that has overshot its commission­ing deadline is the 40-MW Thottiyar scheme in Idukki district.

According to the KSEB, 93.29% of the work on this project is over. The ₹280crore project also has had a chequered history and is still awaiting commission­ing.

Other projects on which work is in progress include the 24-MW Chinnar small hydro project (scheduled for commission­ing in July this year) and the 40-MW Mankulam hydel project, which is due in May 2026.