Integrated Bus Terminus to be opened in July

-

Nearly 200 workers have been deployed at the site of the Integrated Bus Terminus at Panjapur in Tiruchi.

With the constructi­on work reaching the ˜nal stages, the Tiruchi City Corporatio­n plans to open the Integrated Bus Terminus at Panjapur on the Tiruchi-Madurai Highway in July.

It was with the aim of shifting the Central Bus Stand from Cantonment, which has been struggling to cope with the sharp increase in the number of passengers and private and State-owned buses, the Corporatio­n decided to build an integrated bus terminus at Panjapur and began the constructi­on work in October 2022.

It is being taken up at an estimate of ₹349 crore. While the Corporatio­n contribute­s ₹50 crore from its general fund, the grant from the State government stands at ₹140 crore and

the Tamil Nadu Urban Finance and Infrastruc­ture Developmen­t Corporatio­n Ltd. (TUFIDCO) contribute­s ₹159 crore as loan.

Though the civic body originally planned to complete the constructi­on work by December last, it could complete only around 65% of the work and it consumed more time and energy for the foundation work and raising columns. Work for laying platforms and the multiutili­ty centre, which would house small shops, restaurant­s, oŸces, and a mini hall, began only in March 2023.

Minister for Municipal Administra­tion K.N. Nehru visited the constructi­on site at least once in two or three weeks till the Model Code of Conduct came into force. Similarly, Director of Municipal Administra­tion S. Sivarasu visited the site twice to expedite the work.

A senior oŸcial of the Corporatio­n told The Hindu that 85% of the work had been completed in phase-I. The work was divided into basement portion and non-basement portion. Almost all civil works of the ground and ˜rst ¢oor were completed. Roof work of the basement portion had been completed. Plastering work were over. All ramps were completed.

Electrical and plumbing work had been taken up in full swing. Similarly, woodwork was on. More than 200 skilled and semi skilled workers had been engaged at the site. Instructio­ns were given to the contractor­s to complete the work by June. The Corporatio­n would be in a position to operate buses from the new Integrated Bus Terminus. It would most likely be inaugurate­d in July.

 ?? M. MOORTHY ?? Work in progress:
M. MOORTHY Work in progress: