The Sunday Guardian

DefeNce psUs, ordNaNce factories are iN dire Need of overhaUl

As is the case with the DRDO, many of the other DPSUs are engaged in producing non-defence items.

-

India’s nine Defence Public Sector Units ( DPSUs) and 41 Ordnance Factories (OF) are in need of a serious review, overhaul and some serious and meaningful accountabi­lity. This is paramount if India has to achieve a credible level of self- reliance in defence equipment. The problems are myriad. These state-owned DPSUs and OFs hardly invest in research and developmen­t (R&D). They need sufficient resources to undertake upgrading, modernisat­ion and expansion, but not without putting serious accountabi­lity systems into place. They have been suffering serious capacity under-utilisatio­n, are in need of greater financial autonomy, as well as more autonomy in decision making such as in matters relating to joint ventures, co- developmen­t and coproducti­on with foreign countries.

As is the case with the Defence Research and Developmen­t Organisati­on (DRDO), many of the other DPSUs are similarly engaged in producing nondefence items, which has resulted in dilution of their status and character as DPSUs. For example, Bharat Earth Movers Limited (BEML) is heavily into making rolling stock such as wagons and coaches for Railways, earth moving equipment and engaging in mining constructi­on business, with defence accounting for less than 50%. About 20% of products manufactur­ed by Bharat Electrical­s Limited (BEL), which is otherwise entrusted in manufactur­ing radars, sonars, electronic warfare, communicat­ion and other sensor equipment, comprise several major non-defence items such as, for example, electronic voting machines and studio equipment.

The Mishra Dhatu Nigam Limited ( MIDHANI), establishe­d in collaborat­ion with a French and German firm to achieve self-reliance in strategic materials such as special steels, super alloys and titanium alloys for the defence, nuclear and space sectors, has hardly undergone any worthwhile modernisat­ion and remains saddled with outdated and obsolete facilities, and is thus fraught with jeopardisi­ng strategic products. The impact is evident as it is unable to make even the much needed lightweigh­t bullet-proof jackets for the Army and the paramilita­ry forces. Instead, these are mostly being imported. Bharat Dynamics Limited, which makes various types of short range missiles, has a poor track of completing new projects.

The four shipyards comprising the nine DPSUs need major restructur­ing and integratio­n in order to synergise their resources, the lack of which is hindering modernisat­ion of the existing facilities and also in optimising utilisatio­n of human resources and production capacity. It is no wonder that none of the shipyards have been able to obtain a major export contract. Rather India’s defence shipyards remained underutili­sed during much of the 1990s and even a part of this century. And when tasked, they take far too long to construct ships for which the Navy too has to share the blame. Moreover, the shipyards hardly engage in R&D, forcing them to be therefore dependent either on designs supplied by vendors or on designs that are vintage.

One example pertaining to the GRSE’s (Garden Reach Shipyards and Engineerin­g Limited) poor track record should suffice. In March 2003, the government sanctioned constructi­on of four anti- submarine warfare Corvettes. Constructi­on of the four warships were to begin in 2004, 2005, 2007 and 2008, respective­ly, and to be delivered within four years each in 2008, 2009, 2011 and 2012. Instead a series of delays led to an almost three-fold cost escalation from an originally projected Rs 3,000 crore to over Rs 8,000 crore. Eventually, constructi­on on the first ship ( INS Kamurta) began in 2006 and was delivered eight years and two months later in July 2014; the second (INS Kadmatt) eight years and seven months later in November 2015; the third (INS Kiltan) a staggering nine years and seven months later in October 2017 and the fourth (INS Kavaratti) also after over nine years later in 2018. It did not help that the Navy made 1,200 design changes during the course of constructi­on of these ships.

India’s premier naval shipyard, the Mazagon Docks Limited (MDL), has a similarly poor record of maintainin­g deadlines. For example, there were inordinate delays in the delivery of the three 7,400-tonne Kolkata class stealth Destroyers. Delivery of these warships was originally scheduled for 2008, 2009 and 2010. The delivery schedule was first revised to May 2010, May 2011 and May 2012; then further revised to March of 2012, 2013 and 2014, only to be eventually completed in July 2014 (INS Kolkata), followed by in September 2015 (INS Kochi) and November 2016 (INS Chennai) at a 225% escalated cost of Rs 11,662 crore, from the originally estimated Rs 3,800 crore. The delays were on account of multiple problems which included a staggering 2,363 design modificati­ons by the Navy to incorporat­e new weapon systems and sensors, slow constructi­on procedures, technical problems, Ukraine’s failure to deliver the ship’s propellers and shafts, resulting in the contract being later awarded to a Russian firm and finally the delay in the delivery of the Israeli Barak-8 anti-air missiles.

While the Goa Shipyard Limited (GSL) and the GRSE can only build small and medium size ships, India effectivel­y has only one shipyard, the MDL, with the capacity to build large size warships such as destroyers and submarines. Both the GRSE and MDL are fraught with limitation­s and require expansion, if not relocation. Both the GRSE’s future and its ability to build bigger vessels are impeded by the decay of the Kolkata port and the low draft of the Hooghly River. Consultati­ons have been on with western firms to help modernise both the GSL and GRSE, but so far little has been achieved. MDL too has a limited capacity for expansion because of limitation­s of draught (4.5 meters) and its sandwiched location between the Port Trust and a ship breaking yard. Many of India’s 41 OFs, 16 of which were inherited at the time of Independen­ce, are of World War-II vintage and structural­ly inefficien­t. They do not engage in their own R&D and are unable to decide their own vendors. The OFs are primarily manufactur­ing defence products based on transfer of technology from the original equipment manufactur­ers, mostly overseas based and from the DRDO. It has made only modest progress in R&D despite creating 11 Ordnance Developmen­t Centres with identified core technologi­es. Rather, there continue to be complaints of defective ammunition being produced in the OFs which have had to be returned. For example, between 2012 and 2015, 429 different types of defective equipment including ammunition produced at the OFs were returned by the armed forces due to quality issues. There have also been long gestation periods to develop and increase capacities at these factories. It took nine years ( from May 2002 to August 2011) for the Ordnance Factory Board to create a per annum capacity of building just 30 Indian-made Arjun tanks. It took six years to create the per annum capacity of assembling 100 Russianmad­e T-90 tanks and has been unable to increase this capacity to 140 despite efforts since 2011. After four to five years of effort, it has been unable to add even 50% success in increasing the capacity for assembling Russian-supplied T-72 tank variants, manufactur­ing armoured vehicle engines from 350 to 750 per annum and augmenting the capacity to manufactur­e spares needed to overhaul T-72 and T-90 tanks.

The manufactur­ing technology has either been procured on a transfer of technology basis or what has been handed to them by the DRDO, much of which is low- end. The OFs are known not to have a system to prepare a balance sheet in order to have an appraisal of their cost of products and materials. Even a standard accounting system and technical audit by an independen­t agency has not been introduced in the OFs. The private sector is estimated to produce ten times more than what the 41 OFs put together produce despite having two lakh employees. In order for them to be more progressiv­e, productive, competitiv­e and financiall­y viable, OFs could perhaps be turned into a corporatio­n on the lines of, for example, the Indian public sector telephone company, the Bharat Sanchar Nigam Limited (BSNL) and allow them to select vendors and to take a decision in financial and in R&D matters independen­tly.

Clearly, the problems are known. But solutions have to be found and enforced on a war footing. Any derelictio­n is inexcusabl­e if self-reliance is to be achieved. Dinesh Kumar is a defence analyst.

 ??  ?? In March 2003, the government sanctioned constructi­on of four anti-submarine warfare Corvettes. INS Kadmatt (pictured here) was delivered eight years and seven months later than the targeted year i.e. in November 2015.
In March 2003, the government sanctioned constructi­on of four anti-submarine warfare Corvettes. INS Kadmatt (pictured here) was delivered eight years and seven months later than the targeted year i.e. in November 2015.

Newspapers in English

Newspapers from India