Road boost
‘ This contract is officially underway and the council’s Transportation Section will have a start up meeting with the consultant early next month.”
She says their is a 10 month period to take the project through the CPO statutory process to the end of the oral hearing. ‘ Thereafter the decision to grant the CPO or otherwise will be in the hands of An Bord Pleanala. Beyond that then we anticipate a 7 month period to prepare contract documents and complete the tender process and a 9 month construction period.’
She says she will try to push the project to an early as possible finish. ‘ The progress of the Spine Road has been a priority for me since I was first elected,’ she stated.