NEW POWER PLANT

- BY HUBERT MURPHY

SSE is developing a proposal for a 208MW peaker power generation plant at Platin on land owned by the company.

The developmen­t will comprise of four open cycle gas turbine units, each fully enclosed in their own housing, associated stepup grid transforme­r units, and a 110kV transmissi­on substation which will connect the generation plant to the national electricit­y 110kV transmissi­on system.

The company says, ‘ The proposed developmen­t would provide strategic support to the national electricit­y system during peak times, and so would assist in

ensuring and maintainin­g security of supply in the region, providing electricit­y backup at times when customer demand exceeds generation supply.’

Planning permission to use the Platin site for power generation has previously been granted by both Meath County Council and An Bord Pleanála on three prior occasions. Previously approved developmen­ts on the site have included a 400MW combined cycle gas turbine power generation plant and a 60MW peaker power generation plant.

They add, ‘SSE expects to submit two separate applicatio­ns for planning permission to Meath County Council and An Bord Pleanála in respect of the developmen­t – one applicatio­n to Meath County Council for the generation plant and one applicatio­n to An Bord Pleanála for the substation via its Strategic Infrastruc­ture Developmen­t (SID) process.

‘It should be noted that An Bord Pleanála has the power to direct that the entire developmen­t be submitted to the Board for permission/approval as a single applicatio­n via its Strategic Infrastruc­ture Developmen­t (SID) process. Should this occur, SSE will inform the community of this change and advise the community of the process associated with the revised consenting route.

‘Emissions from the site will be generated from the combustion­of distillate oil, which is used to power the gas turbines. A full air dispersion computer model of the emissions has been completed. A number of mitigation measures will be implemente­d during the constructi­on and operationa­l phases of the plant to ensure that atmospheri­c emissions do not have any significan­t adverse impact on ambient air quality.’

The company say the constructi­on period will run for approximat­ely 18 months. During this period the majority of constructi­on personnel vehicles will arrive to site prior to morning rush hour and leave after evening rush hour.

‘A Constructi­on Management Plan will be developed to effectivel­y manage traffic movements to and from the site, as well as other relevant environmen­tal aspects of the constructi­on phase. Once operationa­l, the peaker power generation plant will be run under automated control and will be minimally attended. The average daily traffic is anticipate­d to be approximat­ely three passenger cars and five heavy goods vehicles to and from the site per day. During peak operationa­l periods this may increase to a maximum of five passenger cars and nine heavy goods vehicles. A decelerati­on lane will be put in place on the R152 for traffic turning left into the site from the direction of Drogheda.’

They add that as with all SSE developmen­ts, there will also be opportunit­ies for local community funding.