Irish Independent

Wind-turbine noise ruling from High Court referred to attorney general

- CAROLINE O’DOHERTY

Landmark decision opens possibilit­y of compensati­on

The attorney general is studying a landmark High Court ruling on noise from wind turbines that could have implicatio­ns for the operation of existing and future wind farms.

Officials from two Government department­s, Housing and Environmen­t, have joined the chief law officer in examining the judgment.

Wind Energy Ireland, which represents most wind farm owners in the country, also has experts scrutinisi­ng it.

The ruling found that turbine noise – even if within planning regulation limits – could be categorise­d as a nuisance.

That opens the possibilit­y of compensati­on claims by people who say noise from turbines interferes with the enjoyment of their homes and daily lives.

In the case that gave rise to the ruling, nuisance was proven by two couples who lived close to a wind farm in Co Wexford.

The case heard they were constantly stressed and sleepless, that one of the couples split up largely because of it and one party was left suicidal and remained under treatment for depression.

High Court judge Ms Justice Emily Egan found they had establishe­d their right to receive damages from the company.

“This is wind turbine noise that an objectivel­y reasonable person should not be expected to tolerate,” she said.

A second part of their case will consider the level of damages due and, significan­tly, whether an injunction should be granted against the wind farm.

If an injunction is granted, it may come in the form of restrictio­ns on operating hours rather than a complete stop to operations.

The ruling is the first on the issue in Ireland and comes at a critical time in national plans to increase the generation of renewable electricit­y.

Ireland has about 4.5 gigawatts (GW) of onshore wind power installed in just over 300 wind farms. Under the Climate Action Plan, the capacity must double to 9GW by 2030.

A spokespers­on for Wind Energy Ireland said: “It’s a very detailed judgement and covers a complex area of project developmen­t.

“We are studying it closely to see what implicatio­ns, if any, it might have for the developmen­t of onshore renewable energy in Ireland.”

The Department of Housing, which is responsibl­e for planning regulation­s, said it was considerin­g the judgement in conjunctio­n with the Department of the Environmen­t and the Office of the Attorney General.

The wind farm at the centre of the case is at Ballyduff, Enniscorth­y, Co Wexford, owned by Meenaclogh­spar Wind, and has been in operation since 2017.

It received planning permission with conditions around the level of noise measured at the nearest house.

Over 51 days of hearings, evidence was presented on the causes and frequencie­s of noise, the weather and geographic­al features that influence it and how it is perceived by people.

Lawyers for Meenaclogh­spar said their client should be judged on their compliance with the planning conditions on noise levels, which was not in question.

Ms Justice Egan disagreed, saying the court did not have to restrict its assessment to planning compliance – a finding that may have implicatio­ns in other cases.

She highlighte­d a lack of regulatory data in Ireland, and relied on the UK’s ‘Windfarm Noise Statutory Complaint Methodolog­y’ for guidance.

Ms Justice Egan acknowledg­ed the wider significan­ce of the case.

“This case concerns the production of renewable energy which is clearly of vital importance to society, and to everyone who lives in it,” she said.

The fact that such activity was of public importance was not a defence, she said. However, it might have some bearing on the final outcome.

“The public interest must inevitably be a factor in the court’s assessment of an appropriat­e remedy. At the very least, it means that a generalise­d injunction ought not to be granted where a tailored injunction more suitable to the particular interferen­ce held to constitute nuisance is warranted.”

Current wind energy planning guidelines date to 2006 and are widely accepted to be out of date.

The Department of Housing published draft revised guidelines in 2019 but they were later withdrawn, partly due to disputes over the proposed guidance on noise levels. The Climate Action Plan sets a timeline of the end of this year for completion.

 ?? Photo: Getty ?? The ruling found even within permissibl­e limits, the noise could be classified as a nuisance.
Photo: Getty The ruling found even within permissibl­e limits, the noise could be classified as a nuisance.

Newspapers in English

Newspapers from Ireland