Irish Independent

Couple being sued by solar panel firm allege installati­on fell far short of what they expected

O’Donovans tried to cancel contract after handing over €3,600 deposit

- AMY MOLLOY

A couple who were issued with court proceeding­s after they tried to cancel a contract with a solar panel company claim the product and service they received was not up to the standard they expected.

Sean and Maria O’Donovan paid a deposit of €3,600 to The Energy Centre in Duleek, Co Meath, for the installati­on of 10 solar panels at their home in Ballincoll­ig, Co Cork.

They were unhappy with the service and notified the company last December that they wished to withdraw from the agreement.

However, last month The Energy Centre initiated District Court proceeding­s against the couple, seeking payment for an outstandin­g balance of €6,900.

In a defence filed this week, the couple claim there were significan­t delays with the installati­on.

They allege their consumer rights were infringed because the company did not go through any of the terms and conditions before they entered into an agreement.

On July 27 last year, the couple paid a deposit after a salesperso­n from the company called to their home.

The Energy Centre claims the solar panel system “as agreed was duly installed and the claimant duly complied with its obligation­s as per the agreement with the respondent­s”.

The O’Donovans wanted to install a four-kilowatt system with 10 panels. Following an engineer’s assessment by the Energy Centre, it was deemed that this system would not fit on the roof.

Instead, it was verbally agreed that a smaller system of eight panels (3.2kW) would be installed.

The couple claim a new contract reflecting the change was not provided. They are also alleging that the system was not installed in the manner they expected.

In a statement of counter-claim, they said: “A ‘no-fuss one-day installati­on’ turned into seven days over five weeks.”

An invoice was furnished by The Energy Centre on September 4, 2023, seeking the outstandin­g balance of €6,900. However, the O’Donovans claim the system was not yet working at this point.

It was up and running by October 2, but they claim there was an issue with the system that resulted in it going offline for two weeks in November.

On December 7, they advised The Energy Centre of their intention to withdraw from the purchase. They sought the return of their deposit and asked for the company to collect its solar panel equipment.

They again notified the company by email on December 20 and by registered post on January 8.

A week later, the Energy Centre sent a solicitor’s letter demanding payment for the outstandin­g amount.

The O’Donovans claim the goods they agreed to purchase were not of an acceptable standard or quality.

They claim they have suffered loss, damage and inconvenie­nce as a result.

When contacted by the Irish Independen­t, The Energy Centre said it was “waiting on legal advice as this is now a legal matter”.

The company is a renewable-energy service provider that installs solar panels to generate electricit­y and solar thermal panels that produce hot water.

‘They notified the company last December that they wished to withdraw from the agreement’

Newspapers in English

Newspapers from Ireland