The Avondhu

Extension works commence at Fermoy Community Hospital

- Hu KATIE GLAVIN

The arrival of a Portakabin and workmen wearing hard hats and hi-visibility vests at Fermoy Community Hospital this week was a welcome sight. A spokespers­on for the HSE has confirmed to The Avond

that work at the hospital commenced

on Monday, June 28.

With major changes set to get underway at the Fermoy Community Hospital, a new Director of Nursing, Michelle Kiely, has also been appointed ahead of the commenceme­nt of works.

The project, which received planning permission in the Summer of 2019, includes the constructi­on of a new single-storey extension to the existing Sonas Ward, an extension to the Dochas Ward and an extension to the current kitchen area at Fermoy Community Hospital.

Through the developmen­t, 8 new single bedrooms, a treatment room, a nurses station, additional storage, staff changing facilities and a delivery office as well as numerous other upgrades to various areas in the building and on the grounds would also be completed.

After planning permission was confirmed, it is understood that constructi­on work was to commence shortly thereafter, however, the developmen­t was only put to tender in March, as confirmed by the HSE.

It’s envisaged that the building works will take 15 months to complete, and will be undertaken in such a way as to minimise disruption to the hospital’s long-stay patients.

Works to the hospital were recommende­d by HIQA following a report in 2019 which stated that bedroom accommodat­ion in one of the hospital’s three units “does not support the provision of privacy and dignity to residents”.

The HIQA report noted that, despite a commitment that planned works would be complete by July 2020, constructi­on work that was due to commence in July 2019 had not been started.

“A condition is attached to the registrati­on of the centre, based on commitment­s given by the provider, that the planned works would be completed by July 2020 and the centre would then be in compliance with regulation­s and standards. To meet that timeline, constructi­on work was proposed to commence in July 2019,” the report said.

With the impact of Covid-19 on many sectors, including constructi­on, developmen­ts at the hospital were delayed for some time, however this week, the HSE confirmed that works have now commenced.

Chairperso­n of the Fermoy Community Hospital Fundraisin­g Committee, Tadhg O’Donovan, stated that he welcomes the fact that workers are now on site.

“The bottom line here is that we have been waiting a number of years for this and these are works that will bring the hospital into compliance with HIQA’s recommenda­tions. I welcome these works as it will mean that the hospital will have a future going forward,” Mr O’Donovan said.

 ?? (Photo: Katie Glavin) ?? A spokespers­on for the HSE confirmed that works to Fermoy Community Hospital commenced on Monday. Necessary equipment for the project was being brought to site this week.
(Photo: Katie Glavin) A spokespers­on for the HSE confirmed that works to Fermoy Community Hospital commenced on Monday. Necessary equipment for the project was being brought to site this week.
 ??  ??

Newspapers in English

Newspapers from Ireland