The Irish Mail on Sunday

NEW CHILDREN’S HOSPITAL COSTS ‘OUT OF CONTROL’

Donnelly must ‘come clean’ on bill, insists PAC

- By John Drennan and Nicola Byrne

HEALTH Minister Stephen Donnelly has come under fire over the snowballin­g bill for the National Children’s Hospital as sources close to the project revealed constructi­on costs are ‘galloping away’ due to hyperinfla­tion and soaring wage demands.

Several members of the Dáil Public Accounts Committee (PAC) called on the minister to provide up-to-date costings for the developmen­t, which has been beset by delays and cost overruns.

PAC member Neasa Hourigan, who is also chairperso­n of the powerful

Budgetary Oversight Committee, told the Irish Mail on Sunday: ‘There is huge concern that the costs are now out of control.’

Chronic labour shortages are also adding to the single biggest developmen­t in the State amid escalating tensions between the main contractor and the Government over more than 900 disputed cost claims.

The latest revised budget for the developmen­t is estimated at €1.73bn, making it one of the most expensive hospital projects in the world. However, a source close to the project said this revised price tag is also now ‘unrealisti­c’.

The source told the MoS: ‘The goalposts have changed many times since we started this project but the last 12 months have seen the biggest challenges of all.

‘The constructi­on costs are soaring. We had Brexit and we had the pandemic and labour shortages. Now the pandemic is over but the housing crisis means Dublin is not an attractive place to be.

‘We should have 2,000 workers in an optimum situation and we’re not hitting that. Our constructi­on partners have had to raise wages – that’s a cost. Then there’s the building materials. They’re up 20% due

‘Materials up 20% due to Brexit and Ukraine’

to Brexit, and now Ukraine.

‘That’s all on the price tag. The estimated final cost for the entire project being floated last year was €1.7bn – that’s unrealisti­c now.’

Neither the Department of Health, the Children’s Hospital nor the main contactor BAM, were able to say how much the project will cost the taxpayer by the time it is completed, when contacted by the MoS.

Mr Donnelly has acknowledg­ed the NCH project will cost more than the revised €1.73bn budget, but insists he does not know how much the taxpayer will eventually have to fork out to fund the hospital.

In response to parliament­ary queries from Sinn Féin TD and PAC chairman Brian Stanley, Mr Donnelly said of the €1.73bn estimate, ‘There are a number of items not included in this investment figure as there was no price certainly for them and nor can there be, for some, for the duration of the project’.

He added: ‘These include constructi­on inflation, the impact of Covid-19, statutory changes, any change in scope resulting in healthcare policy changes, and the Employment Order.

‘Brexit, the pandemic and recent geopolitic­al developmen­ts have severely impacted supply chains and the NCH project is not immune to these external challenges.’

And while Mr Donnelly insists work on the NCH site at St James’s Hospital in Dublin ‘is ongoing and progressin­g well’, he was unable to give a concrete timeframe for its completion.

‘The National Paediatric Hospital Developmen­t Board has advised that the main contractor’s current schedule outlines completion can be achieved by December 2023 which would mean the NCH at St James’s could open in the second half of 2024,’ he said in response to parliament­ary queries.

However, Green TD Neasa Hourigan accused Mr Donnelly and the Department of Health of refusing to provide the PAC with details on costings and issues with the contractor. She told the MoS: ‘It is not just that it is spiralling out of control, it is that we have so little informatio­n, they have not given us details of costings, it is incredibly opaque. It is a huge concern in PAC that we have so little informatio­n in PAC on the actual numbers.

They have consistent­ly not given us details of costings, not given us details of issues in question with the developer.’

PAC deputy chair and Social Democrats co-leader Catherine Murphy also criticised the lack of transparen­cy surroundin­g spending and timelines.

Ms Murphy told the MoS: ‘We do not know how much further beyond €1.7bn spending will get.

‘The number of claims BAM have lodged together with building inflation which is written into the tender are a major cause of concern. The project has gone on years longer than projected, partly due to how it was handled in areas such as not enough constructi­on workers.

‘There is real concern in PAC about costs escalating further with no knowing how much beyond €1.7bn it will get,’ she said.

‘All informatio­n is now a closelygua­rded secret. The object for PAC is to ensure costs don’t escalate.’

She added: ‘We are very concerned at this stage it will breach €2bn and the absence of informatio­n increases concern about spending controls.’

At the PAC meeting on March 24, the committee chair complained that correspond­ence from department secretary general Robert Watt failed to address members’ queries and concerns about rising cost levels and staff shortages.

‘Each month this project is prolonged impacts on the cost. Inflation in the costs of constructi­on, especially in the prices of timber, steel and other such materials, is skyrocketi­ng. The reply [from Mr Watt] falls very short,’ said Mr Stanley.

Sinn Féin health spokesman David Cullinane said delays and cost overruns had turned the children’s hospital project into ‘a never-ending saga’.

The Waterford TD added: ‘The project is certainly heading towards €2bn and may even go beyond. There are huge additional costs and disputes where all we are seeing are rising costs and broken timelines – it has gone beyond control.’

Independen­t TD Seán Canning, a former quantity surveyor and lecturer in building and civil engineerin­g, said simply keeping a major site open can add a fifth to the final bill.

Mr Canning said: ‘Outside of the cost of building, if there is a time delay the costs alone of keeping a site open could be between 10% and 15% – security, cranes, machinery, hoarding, electricit­y and maintainin­g workers on site.

‘The costs in material is unquantifi­able, but if you add in inflation that’s another 6%, at a minimum,’ he said.

Latest figures published by the Central Statistics Office reveal the cost of building and constructi­on materials has risen by 17.7% in the year to February.

The latest data also shows productivi­ty in the constructi­on sector remains below 2010 levels and is less than the EU average, again highlighti­ng the huge lack of skilled tradespeop­le needed to complete State developmen­ts and housing projects.

Soaring costs, labour shortages and the recent influx of more than 20,000 Ukrainian refugees are also threatenin­g to derail targets to build 33,000 new homes a year under Minister Darragh O’Brien’s Housing For All plan.

Amid growing concerns over the NCH project, industry sources this weekend warned rampant inflation could bring the constructi­on of schools and hospitals to a halt.

One source told the MoS: ‘Contractor­s are losing millions on rising costs as their public works contracts are fixed price and no increases can be recovered.’

This was echoed at a recent meeting between the Constructi­on Industry Federation (CIF) and Public Expenditur­e Minister Michael McGrath.

CIF director general Tom Parlon warned hyperinfla­tion is creating ‘exceptiona­l challenges’ within the sector, increasing the likelihood of some contractor­s being unable to

‘They won’t provide PAC with the costings’

‘Huge costs – it has gone beyond control’

tender for projects and potentiall­y becoming insolvent.

The CIF is seeking for an effective price variation clause to be included in all new public works contracts and for that mechanism to be applied retrospect­ively to all projects currently under way.

And Mr Parlon warned: ‘If the system isn’t altered… contractor­s will be unwilling to tender for public contracts. It will also have implicatio­ns for projects that are already at the constructi­on stage, as it may become uneconomic­al for some of the contractor­s involved to complete their work without turning insolvent.

‘These are very real risks at the moment, and they will have to be addressed if the public works are to keep progressin­g.’

In response to queries from the MoS, Mr McGrath acknowledg­ed contractor­s are carrying a very significan­t amount of risk with public price contracts.

He added: ‘In making any changes in this area I have to strike an appropriat­e balance between protecting the interests of taxpayers. I will be meeting my officials again next week to examine the options open to me.’

A spokesman for BAM said the contractor ‘is precluded from making any comment’ under the terms of its contract.

The Children’s Hospital Group did not respond to queries for comment this weekend.

 ?? ?? costly: Plans for the National Children’s Hospital
costly: Plans for the National Children’s Hospital
 ?? ??
 ?? ??
 ?? ?? hike: Rise in constructi­on materials will push the bill up further, fears Neasa Hourigan
hike: Rise in constructi­on materials will push the bill up further, fears Neasa Hourigan
 ?? ?? futuristic: How the project will look when finished
futuristic: How the project will look when finished

Newspapers in English

Newspapers from Ireland