The Irish Mail on Sunday

CHAOS BEHIND NCH FINAL BILL

● Total spend will go ‘way over’ €2bn says hospital insider ● ‘Nobody can tell you how much it will end up costing’ ● PAC vice-chair says money will run out ‘early next year’

- By Colm McGuirk and John Drennan

THE final cost of the National Children’s Hospital is set to be well north of €2bn, an insider has told the Irish Mail On Sunday.

And the massive final bill has less to do with pandemic-related delays and constructi­on inflation than the fact that contracts were awarded before plans were completed, according to a source who has worked on the project.

It comes as pressure mounts on Health Minister Stephen Donnelly and secretary general at the Department of Health Robert Watt over a lack of transparen­cy on the costs.

Public Accounts Committee chairman Brian Stanley was sharply critical this week of the ongoing refusal of Mr Watt to provide the committee with sufficient informatio­n on the ‘live status of the current budget’.

And his vice-chair, Social Democrats coleader Catherine Murphy, told the MoS the State will run out of money for the

completion of the National Children’s Hospital a year before the contractor­s expect to leave the site.

Originally, the contract with the developers had a scheduled completion date of December 2023 with a final bill rising to €1.73bn.

However, constructi­on delays and legal conflicts mean this could extend out to the end of 2024 with uncertain fiscal consequenc­es.

A constructi­on executive who worked on the project told the MoS this week that the site is still chaotic.

‘There are contractor­s working on that job today who don’t have a design.

‘The Government can attempt to massage figures to underplay the final spend but the true costs will certainly go way over €2bn.’

The source said when he was working on the project, he was ‘sitting in an office, and there were lots of people on the job and they didn’t have a design and they were already on site’.

He said the design issues were ‘at the heart and the root cause of a lot of the problems on that job’.

‘Plus, the original allowances, a lot of it wasn’t designed. So you had quantity surveyors making assumption­s and putting figures against things, which had turned out to be multiples wrong.

‘Not wrong because they didn’t know, but when the design was actually done, the level of finish, the cost would have spiralled in comparison to original estimates.

‘It was always going to. If you design an external facade that’s completely curved and made of glass, you’re only asking for trouble.

‘It was never going to even remotely come in at the original figures. You don’t need to be a rocket scientist to know that. Anyone who gives an answer is basically just lying to you.

‘It’s not a figure anyone could give with any science whatsoever.’

The project is also being delayed by more than 1,000 claims and adjustment­s submitted by the contractor with a value in excess of €500m.

Commenting on the challengin­g fiscal landscape, Ms Murphy said: ‘The NCH is probably going to be the most expensive hospital in the world. We don’t know what the ceiling is.’

She expressed special concern over the HSE running out of money at least a year before the end of the current contract.

The final amount budgeted by the HSE for the build is €1.73bn.

But, she said that ‘given this is not now scheduled to complete until 2024, there will have to be further interventi­on by the Government’.

Commenting on the current budget allocated to the hospital, she said: ‘Early next year the pot will be empty. There will be nothing to draw-down. The Department [of Health] will have to go to the taxpayer again looking for another pot of money.’

As speculatio­n over the final bill spirals, concern is rising within the PAC that the State’s primary accountanc­y body is being ‘left in the dark’ over the final costs of the National Children’s Hospital.

Both Mr Stanley and Ms Murphy were sharply critical of the ongoing refusal of Mr Watt to provide the committee with sufficient informatio­n. They were referring to a key review into the NCH by the National Paediatric Hospital Developmen­t Board (NPHDB) and the Department of Health.

Originally the PAC was promised access to the report but, on the accession of Mr Watt, this was withdrawn on the grounds of ‘commercial sensitivit­y’.

Mr Stanley told the MoS that ‘in the absence of the report the spend is open-ended and the taxpayer is utterly defenceles­s’.

The Sinn Féin TD added: ‘We were promised sight of that report a year ago and the committee has yet to see it thanks to the opposition of Mr Watt.’

Mr Stanley warned that when it came to the issue of escalating costs ‘at this late stage the State and the taxpayer have been put in a bad place by the two-stage process’. He added: ‘Realistica­lly it is impossible to move BAM [the main contractor­s] off. That ship has sailed.

‘Even if BAM were removed, it is more difficult still to get a new contractor in a situation where everything is bogged down in litigation.’

The situation, he said, had ‘not been improved by the scenario where, when it comes to the provision of informatio­n, we are fighting with one hand tied behind our backs. We are utterly operating in the dark. We are restricted in the informatio­n we can secure’.

The PAC is especially concerned over the role played by Mr Watt who headed the Department of Public Expenditur­e when the current contract was signed. Mr Stanley said: ‘It is less than satisfacto­ry that the person who essentiall­y decided and had responsibi­lity for the contract has taken the decision to deny access to the PAC. We have drawn a blank on all levels.’ He added: ‘When it came to a cost above €2bn, Robert Watt could not guarantee it wouldn’t go past that.’

The chairman said: ‘My judgment from the informatio­n is that the second half of a contract can be far more costly.’

Deputy Murphy also slammed the culture of secrecy surroundin­g the provision of informatio­n.

She said: ‘We are getting the accounts in retrospect – we are not getting real-time informatio­n.’

And in a signal of potential future spats, she said: ‘Contracts are a two-way process. There is an obligation to hold on to a timeframe. Because of the contractor­s’ delays we have walked into an inflationa­ry spiral. Someone has to be held accountabl­e for this.’

Earlier this year, a source close to the hospital project admitted to the MoS that the costs of constructi­on were ‘galloping away’.

He agreed that the revised €1.7bn price tag was now ‘unrealisti­c’.

He said: ‘The goalposts have changed many times since we started this project but the last 12 months have seen the biggest challenges of all.

‘The constructi­on costs are soaring. We had Brexit and we had the pandemic, and labour shortages. Now the pandemic is over but the housing crisis means Dublin is not an attractive place to be. The estimated final cost for the entire project being floated last year was €1.7bn – that’s unrealisti­c now.’

Neither the Department of Health nor the NPHDB commented when contacted about the constuctio­n insider’s claims. BAM also did not reply to our request for comment.

‘Contractor­s working on the job with no design’

 ?? ??
 ?? ??
 ?? ??
 ?? ?? conflict: PAC vice-chair Catherine Murphy, above, Department of Health secretary general Robert Watt, centre, and PAC chairman Brian Stanley, right
conflict: PAC vice-chair Catherine Murphy, above, Department of Health secretary general Robert Watt, centre, and PAC chairman Brian Stanley, right
 ?? ?? costly: National Children’s Hospital and, right, Stephen Donnelly
costly: National Children’s Hospital and, right, Stephen Donnelly

Newspapers in English

Newspapers from Ireland