The Kerryman (South Kerry Edition)

BORD REFUSES WIND FARM

- By DÓNAL NOLAN

AN Bord Pleanála has upheld a decision by Kerry County Council to refuse a wind farm in Ballylongf­ord.

The Ballylongf­ord Windfarm Group had applied to Kerry County Council to construct eight wind turbines at Aghanagran Lower and surroundin­g townlands in Ballylongf­ord; each with a ground-to-blade tip height of 126.5 m.

Kerry County Council refused permission last year, a decision that was appealed to the Bord by the Ballylongf­ord Windfarm Group on December 4 last.

However, An Bord informed the appellant last week that its appeal was unsuccessf­ul, in a decision that was to have been made public today (Wednesday). An Bord Pleanála confirmed the refusal to The Kerryman last week, but that was all a staff member said it could communicat­e until the publicatio­n of the full decision, to be released after time of press.

The refusal was welcomed by a local group opposed to the further developmen­t of renewables in the area and whose members had objected to the Aghanagran plan.

NMWT@Ballylongf­ord (No More Wind Turbines at Ballylongf­ord) issued a statement on Friday in which it set out its members’ satisfacti­on with the ruling.

It claimed the Bord came to the decision amid concerns for the environmen­t locally, and in the absence of a key assessment having been provided by the wind farm firm.

Chair of NMWT@Ballylongf­ord Tony Dowd said: ‘In their ruling, ABP were concerned about the impact...on the Ballylongf­ord Creek’ and that ‘the applicatio­n by the Ballylongf­ord Wind Farm Group did not contain a Natura Impact Statement.’

 ??  ?? NMWT Chairperso­n Tony Dowd
NMWT Chairperso­n Tony Dowd
 ??  ??