RP2.0 EXPANSION PROJECT
One such project that exemplifies the forefront of Trevali’s high level of operation is the company’s RP2.0 Expansion Project at Rosh Pinah
This project includes a new single stage SAG mill crushing and ore blending system with a nominal throughput increase from 0.7 to 1.3 million tonnes per annum, on top of multiple additional aspects, as Horn comments.
“The RP2.0 Expansion Project also includes a new paste fill plant and reticulation system that will reduce surface tailings and mining dilution while increasing ore recovery,” he informs us, and continues. “A new dedicated portal and decline with associated infrastructure for the Western Orefield Three (WF3) deposit, and underground mobile equipment for the WF3 moving from 30 tonne to 60 tonne haul trucks.
“The capital cost totals approximately $93 million as per the Pre-Feasibility Study published in August 2020, and construction is