Kuwait Times

Delays, cost overrun seen in contested UK nuclear plant

-

PARIS: A project to build a nuclear plant at Hinkley Point in Britain will overrun by £1.5 billion ($1.95 billion, 1.71 billion euros) and may face further delays, its main supplier said yesterday. EDF, the state-run French company that has the lion’s share of the controvers­ial scheme, made the announceme­nt after a long review. EDF is part of a FrenchChin­ese consortium that was awarded the tworeactor project last year despite criticism from green groups and cost warnings from experts. “The final project costs are now estimated at £19.6 billion at 2015 rates, an increase of £1.5 billion,” EDF said in a statement.

The higher estimate derives from “better discernmen­t of the design” and “the volume and sequencing of work on site and the progressiv­e implementa­tion of suppliers’ contracts,” it said. It also warned of a possible delay of 15 months in delivering the first reactor, and nine months for the second. If this risk is confirmed, the deal would add “around £0.7 billion” to costs, EDF said. The announceme­nt came after EDF on June 26 acknowledg­ed that it was carrying out a “full review” of costs and scheduling.

Named Hinkley Point C, the project, built in the southweste­rn English county of Somerset, is being showcased as the first British nuclear power station to be built in more than two decades. It will provide seven percent of Britain’s power needs, replacing old, carbon-emitting coal-fired plants, according to the British government. But the costs and timetable have been repeatedly revised. In 2007, an EDF boss promised that, in 2017, Britons would be able to cook their Christmas turkeys using electricit­y from the facility.

Troubled project

Critics have focused on the proposed design, which uses a novel EPR reactor that has run into huge problems of cost overruns and delays at sites in France and Finland. Yesterday, EDF said that constructi­on work on the first reactor at Hinkley Point was still scheduled for “mid-2019.” However, the date depended on the final design of the reactor, it said. This decision is expected by the end of 2018, but “the schedule is tight,” it admitted.

Detractors also question an electricit­y price guarantee to EDF of £92.5 for every megawatt hour of power produced by Hinkley over the following 35 years, rising with inflation, despite falling energy prices. On June 23, Britain’s National Audit Office (NAO) said the expected cost of top-up payments had ballooned from £6 billion to nearly £30 billion. The deal “has locked consumers into a risky and expensive project with uncertain strategic and economic benefits,” the NAO said. Environmen­talists are also fiercely opposed, urging the government to instead focus on renewable sources like wind and solar power to meet Britain’s energy needs.

The 3,200-megawatt project, scheduled under the deal to go online in 2025, has a designed operationa­l lifetime of 60 years. The deal was approved by Prime Minister Theresa May’s government only last September, amid uncertaint­y about the future of the British economy caused by Brexit. EDF, mainly owned by the French government, is funding around two-thirds of the cost and its Chinese partner, China General Nuclear Corporatio­n,is financing the remainder.

Doubts within EDF

Constructi­on work on non-reactor structures began in March this year, and EDF has already signed major contracts with suppliers such as the French giants Bouygues and Areva and General Electric of the United States. Internal divisions surfaced last year within EDF about pushing ahead with Hinkley Point while the firm struggled with a debt mountain of more than 37.4 billion euros and grappled with the merger of the reactor unit of French nuclear builder Areva. The company’s financial director, Gerard Magnin, quit in disagreeme­nt with the plan. The remaining 17 members of the board approved it by only 10 votes to seven at a crunch meeting on July 28.—AFP

Newspapers in English

Newspapers from Kuwait