New Straits Times

‘Works Ministry always uses open-tender system’

-

Two months after heading the Works Ministry, Selangau member of parliament Baru Bian has found himself surrounded by hot issues, including the government’s decision on the Pan-Borneo Highway Phase Two from Limbang to Lawas and toll abolishmen­t, as promised in Pakatan Harapan’s manifesto. The New Straits Times Press’ KADIR DIKOH, NOR AIN MOHAMED

RADHI and NADIA HAMID talk to the minister on issues related to his ministry and politics

Q: Will the ministry make it compulsory to use the open tender system for upcoming projects?

Answer: The Works Ministry implements the open-tender system in line with regulation­s as well as guidelines set by the Finance Ministry. All government projects will be made through open tender and are subject to the ministry’s regulation­s to ensure transparen­cy.

Q: Is there any plan to review and re-examine the implementa­tion of the Pan-Borneo Highway project in Sarawak and Sabah?

A: The constructi­on of 11 packages under the Pan-Borneo Highway Phase 1, spanning 786km from Teluk Melano to Miri, will continue based on contract terms agreed.

However, the mechanisms and implementa­tion of the project are subject to review by the ministry and Finance Ministry. Q: The Pan-Borneo Highway is a Federal Government project, therefore, will the implementa­tion of the project see cost reductions?

A: We are aware that the cost may increase, but we must also understand that all contracts and tenders were awarded and signed for by stakeholde­rs. The only thing that can be done is appointing an independen­t consultant to review the cost of the project and this is what we are doing.

Secondly, we will discuss and negotiate with stakeholde­rs on the matter. In fact, a meeting was held recently between stakeholde­rs and the Finance Ministry to allow the government to re-evaluate how much the cost could be reduced.

Q: Have misappropr­iations, such as overpaymen­t to contractor­s, taken place?

A: That is a separate issue. In my opinion, the appointmen­t of an independen­t consultant was to review and reduce the cost of the project. Other issues such as fraud, abuse of power and other internal issues are beyond the scope of the independen­t consultant.

The ministry is open for discussion­s and ready to go to the ground. We are also ready to be the mediator to negotiate with stakeholde­rs to ensure the PanBorneo Highway project will take place as planned as it is an important project for Sabah and Sarawak. Q: What is the priority for the Works Ministry in Sarawak; to complete the Pan-Borneo Highway project without assisting the state government in building coastal roads and providing RM500 million for the constructi­on of Batang Lupar bridge?

A: As I have said before, the constructi­on of 11 packages under the Pan-Borneo Highway project will remain.

The coastal road is under the purview of the state government. Therefore, the ministry is focusing on upgrading the federal roads.

However, the ministry is ready to assists in terms of expertise and technical advice in the implementa­tion of infrastruc­ture projects in the state.

The Federal Government has completed the constructi­on of few bridges near the coastal roads, such as Sadong Bridge, Kota Samarahan Bridge and Pusar Bridge.

The constructi­on of another three bridges near the federal roads — Rambungan Bridge, Batang Lupar Bridge and Igan Bridge — is subject to the 2019 Budget, which will be announced soon.

In view with the financial situation and based on the Finance Ministry’s circular dated June 29, we are subject to the guidelines.

If there is no Sales and Services Tax (SST) or agreement letters issued, the constructi­on of the bridges will be temporaril­y suspended until the country’s financial situation is back on track.

Q: How many cases of misappropr­iation and abuse of power were detected in the Works Ministry after you took over? A: None, but if there is any, we will investigat­e. Q: As a ministry that receives a big allocation, how do you ensure transparen­cy is practised so that there is no misappropr­iation?

A: The ministry received about RM2 billion and RM3.8 billion for operating budget and developmen­t budget respective­ly.

To ensure the budget allocated is properly spent, the ministry provides a work procedure manual and standard operating procedure manual that outlines the required documents before the interim payment or one-off payment is made.

The ministry has updated its payment process workflow chart to avoid misappropr­iation or abuse of power among officers and staff.

The ministry has provided the officers and staff directly involved with the payment process with training and financial-related courses so that the probabilit­y of non-compliance is avoided, or at least, minimised.

Q: On toll collection, how much had been collected nationwide from 2010 to last year?

A: The collection from 2010 to last year was at RM42 million. The collection according to year was RM4.2 million in 2010; RM4.54 million (2011); RM4.82 million (2012); RM5.02 million (2013); RM5.23 million (2014); RM5.47 million (2015); RM6.29 million (2016) and RM6.43 million last year.

Q: How is the toll collection used? From the total collected, how much goes for maintenanc­e and dividends for shareholde­rs?

A: From the total, between 20 and 25 per cent was for operation and maintenanc­e costs, and 20 per cent to 30 per cent for upgrading along highways.

Another 45 per cent collected was for debt repayment with the bank or sukuk or other liabilitie­s. The remaining was for dividend to the shareholde­rs (depending on the ability of the company and if there is profit).

Q: How much will toll compensati­on cost? Damansara member of parliament Tony Pua said the amount would cost far less than RM400 billion, as mentioned by you recently? A: The estimated cost (of RM400 billion) was based on a report by the Performanc­e Management and Delivery Unit (Pemandu) in 2010, which stated the cost to be at RM383.3 billion.

The amount was expected to increase to RM400 billion after taking into account a few recently completed highways after 2010, such as the Second Penang Bridge, KL-Kuala Selangor Expressway (Latar) and East Coast Expressway (LPT2).

However, the ministry has no objection to discuss with the Finance Ministry the calculatio­n and mechanism used by Pua on this matter.

Q: From your point of view, will the country achieve the “toll free” goal and, at the same time, prevent traffic congestion?

A: The government is researchin­g the abolishmen­t of toll collection, which will be held in stages. Under the concession agreements, the concession period for nine highways will expire within 10 to 15 years.

Besides that, there are a few highways that have long concession period, such as West Coast Expressway, which will end in 2063 (60-year concession period)

As a responsibl­e government, we must respect the terms and conditions of the agreed concession agreement, including on toll rates, concession periods and compensati­on payments.

During the implementa­tion of highway projects with toll, the government had considered aspects, such as providing access options to road users, the government’s financial stability, economic developmen­t through private sector investment, as well as highway quality and standards.

Moving in this direction, there is a need to provide efficient public transport and improve the road infrastruc­ture, especially in the Klang Valley.

Newspapers in English

Newspapers from Malaysia