The Borneo Post (Sabah)

Kolopis-Segaliud transmissi­on tower near Kampung Kerokot ready

-

TAMBUNAN: Work on the transfer of the 275 kilovolt (kV) Kolopis-Segaliud transmissi­on tower undertaken by Sabah Electricit­y Sdn Bhd (SESB) in the vicinity of Kampung Kerokot, here was completed on Wednesday evening.

According to a statement released by SESB here yesterday, the work was carried out after they found one of the existing tower site was unstable due to the problem of soil erosion.

The commitment and cooperatio­n of all parties involved has resulted in completion of the project planned for 13 days starting from April 1 - 13.

While the work was being carried out, the Sabah Grid system continued its supply as usual despite the energy exports being limited to 120 megawatts IMW) per day compared to almost 200MW under normal conditions.

This was implemente­d as only one line could be used for the supply of electricit­y to the East Coast.

A total of 50 contractor­s and members of SESB were involved with the work on site, while a total of seven mobile generator sets were installed and used in some strategic points to increase the generation capacity in the East Coast.

SESB would also like to express appreciati­on to all those involved, especially the State Government, the Energy Commission, Tenaga Nasional Berhad (TNB), independen­t power producers (IPPs) and 12 user companies superpower (LPC) in Sandakan, Lahad Datu and Tawau which have helped ensure there was no need to implement electricit­y rationing during the constructi­on works of the tower.

Newspapers in English

Newspapers from Malaysia