MRT SSP Line 7.5 pct completed, 18 pct by December

-

KUALA LUMPUR: Mass Rapid Transit Corporatio­n Sdn Bhd (MRT Corp) projects 15 to 18 per cent completion of its Sungai Buloh-Serdang-Putrajaya (SSP) Line by end-2017.

MRT Corp SSP Line Project Director, Datuk Amiruddin Ma’aris, said at present, the overall progress of the MRT SSP Line is at 7. 5 per cent and its constructi­on schedule was on track.

He said MRT Corp had awarded 31 packages worth up to RM30 bilion to-date for the Klang Valley MRT SSP Line, while the remaining 38 packages, valued at RM2 billion, were expected to be awarded by this year and in 2018.

“As all civil and systems packages have been awarded, works have begun for both the northern and southern elevated alignment, undergroun­d section and the depot.

“The SSP Line is now moving at a good pace according to plans,” he told a media briefing on the MRT SSP Line progress update here, yesterday.

A mi rudd in said for undergroun­d works, which included utility relocation, excavation for station boxes and shafts, tunnel boring machine (TBM) refurbishm­ent, as well as manufactur­ing, was progressin­g well at 8.7 per cent.

A total of 12 TBMs would be used to excavate the tunnels for the SSP Line’’s 13.5-kilometre (km) undergroun­d section.

As for the land acquisitio­n progress, he said MRT spent about RM2.2 billion for two-thirds of the lots required for the developmen­t of the SSP Line.