The Borneo Post (Sabah)

Pan Borneo Highway in Sabah to be completed as orginally scheduled

-

KIMANIS: The Works Ministry’s takeover of the constructi­on of the Pan Borneo Highway in Sabah from the project delivery partner (PDP) in September last year proved that the government is committed to ensuring the successful implementa­tion of the project.

In fact, to ensure that the project is implemente­d effectivel­y, the ministry then entrusted that responsibi­lity to the state Public Works Department under the Sabah Infrastruc­ture Developmen­t Ministry.

At the Sabah State Legislativ­e Assembly sitting in November last year, state Infrastruc­ture Developmen­t Minister Datuk Peter Anthony said 12 work packages of the highway project were expected to be completed according to the original schedule of June 2022.

He said three more packages would be completed by the end of 2023 the latest.

The constructi­on of these 15 packages will be continued under the 11th Malaysia Plan, which runs from 20162020, while the remaining 20 packages will be implemente­d under the 12th Malaysia Plan (2021-2025).

The commitment of the federal and Sabah government­s in this matter has debunked the opposition Barisan Nasional’s (BN) allegation in the Kimanis parliament­ary by-election campaign that the highway project has been abandoned.

Former prime minister Datuk Seri Najib Razak had alleged that Pakatan Harapan (PH) had checked BN’s efforts to change the economic landscape of Sabah as the Pan Borneo Highway project was now abandoned.

Last Monday, the Works Ministry said in a statement that the Sabah Pan Borneo Highway project had reached 22 per cent physical completion for the original 12 packages as at December 31, 2019 and it would be fully completed in stages by June 2023.

The ministry also said the three new additional packages are expected to be completed by the end of 2023.

“The implementa­tion period of the 12 contracts has experience­d a slight delay compared to the initial completion date (June 2022) due to, among others, land acquisitio­n process and obstructio­n at the constructi­on site as well as the changes in project implementa­tion method, from PDP to convention­al contract,” said the ministry.

The Sabah and Sarawak Pan Borneo Highway project, which was launched by the previous government in June 2015, involves the constructi­on of 2,333km of major roads in the two states.

Realising the importance of the project to the people of the two states, the PH government has shown its commitment in completing the highway, as stated by Finance Minister Lim Guan Eng in his 2020 Budget speech in October last year.

Lim said the implementa­tion of the project was important to ensure that the infrastruc­ture developmen­t would serve as a catalyst for the economic growth of Sabah and Sarawak.

The PH government has also undertaken a rationalis­ation process to slash the project cost by RM1.2 billion to RM29 billion.

Sabah Chief Minister Datuk Seri Mohd Shafie Apdal, who is also state Finance Minister, has given an assurance that the Sabah Pan Borneo Highway project would be continued using a new formula and approach.

He said the new structure for managing the constructi­on of the multi-billion ringgit highway would reduce its cost.

He said the government had spent RM26 million when the project was managed by the PDP and so far RM900 million had been spent on land compensati­on.

To ensure transparen­cy and proper implementa­tion, Mohd Shafie said, the project would be managed by a body chaired by State Secretary Datuk Safar Untong and comprising representa­tives of the finance and works ministries at the state and federal levels.

Bernama’s checks in the Kimanis constituen­cy show that some contractor­s were carrying out building works on the highway project.

 ??  ?? The constructi­on of Pan Borneo Highway near Jalan Mawao Membakut.
The constructi­on of Pan Borneo Highway near Jalan Mawao Membakut.

Newspapers in English

Newspapers from Malaysia