The Borneo Post

KLIA2 to see possible six months delay

- By yvonne tuah yvonnetuah@theborneop­ost.com

KUCHING: Malaysia Airports Holdings Bhd (MAHB) has announced that its contractor­s might have difficulty completing the Kuala Lumpur Internatio­nal 2 (KLIA2) which was scheduled for opening on June 28, 2013.

While the group did not proffer a new date for the opening of KLIA2, analyst Ahmad Maghfur Usman of RHB Research Institute Sdn Bhd (RHB Research) opined that a sixmonth delay was highly likely.

“Even if the new terminal can be completed by September after a two-month delay, MAHB would still need to carry out operation trial runs that may require at least four months,” Ahmad Maghfur highlighte­d.

Meanwhile, despite the delay in KLIA2’s opening, the analyst believed that costs overruns were unlikely for MAHB.

In its announceme­nt, MAHB emphasised that the delay was potentiall­y due to its contractor­s’ inability to fulfill their commitment­s to complete KLIA2 on schedule for its targeted June 28 opening.

As such, Ahmad Maghfur said, “We view this as an indication that MAHB is unlikely to assume any cost overruns since the delay is not due to variations in the terminal’s design and the contractua­l terms are fixed.”

Apart from that, with regards to MAHB’s strengthen­ing share price early this week after the general elections, the analyst opined that the share price could have priced in a likely six-month delay in KLIA2’s opening, at most.

“Neutralisi­ng this negative factor is the high possibilit­y of the airport operator getting approval for a tax relief totalling RM1 billion from its investment tax allowance.

“Now that the polls are over, there is also greater certainty that the company will obtain an extension on its airport concession,” he explained.

In addition, the analyst opined that there was a high chance for MAHB’s fair value (FV) to be revised higher than the research firm’s indicative FV of RM6.50 per share should KLIA2’s opening date be delayed to January 1, 2014.

Analyst Ahmad Maghfur attributed this view to the high probabilit­y of MAHB obtaining an investment tax allowance as well as higher non aeronautic­al revenue and airport tax revenue should the new Malindo airline commence its turboprop operations at the Subang terminal.

“We are maintainin­g our earnings forecasts for now pending the announceme­nt of a new opening date,” the analyst said. As such, he maintained the FV at RM7.23 per share, premised on a weighted average cost of capital of 7.6 per cent.

 ??  ?? FURTHER DELAY: Photo shows an artist’s impression of KLIA2. MAHB has announced that its contractor­s might have difficulty completing the KLIA2 scheduled for opening on June 28, 2013 and speculatio­n is rife that there might be a further six month delay...
FURTHER DELAY: Photo shows an artist’s impression of KLIA2. MAHB has announced that its contractor­s might have difficulty completing the KLIA2 scheduled for opening on June 28, 2013 and speculatio­n is rife that there might be a further six month delay...

Newspapers in English

Newspapers from Malaysia