The Borneo Post

MRT trial runs to start in October

-

KUALA LUMPUR: Malaysians will get their first feel of the much anticipate­d Mass Rapid Transit (MRT) this October with the commenceme­nt of trial runs.

This was confirmed by Mass Rapid Transit Corporatio­n Sdn Bhd (MRT Corp) Director of Operations and Assets Management, Mahmood Razak, who said the Sungai Buloh-Kajang (SBK) Line will start a three-month trial run from Oct 1, preceding the official launch of operations on Dec 31.

“The phase one of the MRT SBK Line from Sungai Buloh to Semantan, will be almost complete by October, as all civil structural works for the elevated stations and guide ways are complete.

“The overall progress of the MRT SBK Line was at 86.52 per cent as at end-June,,” he told Bernama.

The supporting facilities, including car parks and feeder buses will commence operation by then to start serving the public.

Mahmood said MRT Corp is providing 14 parking facilities of multi-storey and open-air car parks for the 51km-long MRT SBK Line.

“There will be 8,000 parking bays available along the line, with 1,200 at the Sungai Buloh and Kajang stations respective­ly.

The phase one of the MRT SBK Line from Sungai Buloh to Semantan, will be almost complete by October, as all civil structural works for the elevated stations and guide ways are complete.

The rest are at stations along the line,” he added.

Mahmood said Rapid Rail Sdn Bhd feeder buses will cover a threekilom­etre radius around stations with a 10-minute frequency, subject to traffic conditions.

“People can either drive to the stations or be dropped off by public or private transport. For the first phase, 140 buses will be deployed to cover areas around the Sungai Buloh Station to Semantan Stations.

“For the entire line, a total of 300 buses will be available.

“Many aspects has been configured to cater for an integrated public transport,” he added. — Bernama

Mahmood Razak, MRT Corp Director of Operations and Assets Management

 ??  ?? Mahmood is seen showing the MRT line. MRT Corp is providing 14 parking facilities of multi-storey and open-air car parks for the 51kmlong MRT SBK Line. — Bernama photo
Mahmood is seen showing the MRT line. MRT Corp is providing 14 parking facilities of multi-storey and open-air car parks for the 51kmlong MRT SBK Line. — Bernama photo

Newspapers in English

Newspapers from Malaysia