‘Be strict with Siniawan Waterfront project’
SEREMBU assemblyman Miro Simuh has reminded the Sarawak Drainage and Irrigation Department (DID) to act more strictly against the contractors doing the Siniawan Waterfront Development Project.
He lamented that the project, which was handed over to the contractors in November 2019, had yet to see any sign of completion.
“I feel like giving up on asking the DID Sarawak, who is the implementing agency for this project. The project, which should be completed in April 2022, is currently only at 55 percent completed. I urge the implementing agency to act more strictly with the contractors involved, or if necessary, just terminate their contracts and give the project to a new rescue contractor,” he said when debating the State Budget 2023 at the State Legislative Assembly (DUN) sitting yesterday.
On aother matter, Miro appealed to the state government to take over the Bung Muan Tourism Facility Development Project and the Brooke Heritage at Kampung Peninjau in Bau.