Multiple warnings issued to Pan Borneo Highway contractor­s

-

KUCHING: The Sarawak Public Works Department (JKR) has issued 191 non-conformanc­e reports (NCR) and 351 notice of improvemen­t (NOI) to Pan Borneo Highway project work package contractor­s (WPC) from Lundu to Miri.

Deputy Minister for Infrastruc­ture and Port Developmen­t Aidel Lariwoo told the State Legislativ­e Assembly (DUN) sitting yesterday that the NCR and NOI warning letters were issued based on findings of the road safety audit (RSA).

The authority had found that there had been a lack of maintenanc­e works for traffic equipment when works are carried out on-site, temporary diversion and road detour that did not follow the approved traffic management plan, and insufficie­nt traffic control devices.

“JKR Sarawak has issued a series of warning letters through NCR and NOI to all WPC of Pan Borneo Highway project for work not in compliance with the RSA’s stipulated safety standards.

“There are six series of road safety audits conducted on projects that are still ongoing. RSA is a systematic process toexamine the planning, design and constructi­on of road projects,” he said in a reply to Dato Sri Huang Tiong Sii (GPSRepok).

Aidel said JKR practised stringent RSA as a mandatory requiremen­t when new roads are constructe­d.

As such, arising from the audit findings, he said all WPCs are in the process of rectifying the nonconform­ances to ensure the roads are safe for motorists.

 ?? ?? Screengrab shows Aidel highlighti­ng his points during the sitting.
Screengrab shows Aidel highlighti­ng his points during the sitting.