The Star Malaysia

Contractor’s financial woes delay project

-

PETALING JAYA: The constructi­on project for a multi-storey carpark at the Hospital Canselor Tuanku Mukhriz (HCTM) worth RM28.6mil was not completed on time due to the financial constraint­s of its contractor, said the 2015 Auditor-General’s Report (Series 2).

The report noted that the progress of the carpark project at HCTM, which was formerly known as Hospital Universiti Kebangsaan Malaysia (HUKM), stood at 22.3% as of Aug 18 last year.

“The late progress was due to the contractor’s financial constraint­s and the inability to continue the constructi­on work.

“The contract was terminated on Oct 15, 2015 and a penalty of RM314,031 was imposed for the delay,” said the report.

The report said the Public Works Department (JKR) had appointed a new contractor for the project.

UKM received RM10mil under the 10th Malaysian Plan for the project, which would be implemente­d by JKR.

The report said that Universiti Kebangsaan Malaysia and HCTM spent RM1.83bil from 2013 to 2015 on procuremen­t through direct purchases, quotations, tenders and direct negotiatio­ns.

The report found 512 local orders or invoices amounting to RM1.17mil were split into smaller amounts in order to avoid red tape on price quotation procedures.

“The approval for 10 work procuremen­t through direct purchases worth RM92,845 in two residentia­l colleges had exceeded the authorised limit.

“Six of the procuremen­ts, which were supposed to be carried out through quotations, were worth more than RM20,000 each,” it said.

The report revealed that a total of 186 local orders amounting to RM268,892 between 2013 to 2015 were prepared, verified and approved by the same officer.

“A total of RM19,684 was paid to the supplier for eight loud speaker equipment for the Langkawi Research Centre, but was never delivered,” it said..

The research centre, establishe­d in 2002, focused on developing natural resources and research for tourism in Langkawi under UKM.

The report recommende­d HUKM manage its procuremen­ts in accordance with the rules and good governance practices to avoid procuremen­t for the same type of items being split into smaller amounts.

In reply to the Treasury, HUKM said any procuremen­t worth between RM20,000 to RM50,000 must obtain an approval from UKM’s special quotation committee, while procuremen­ts worth between RM50,000 to RM500,000 must be brought to the procuremen­t committee for consent.

 ??  ?? Weaknesses revealed: Performanc­e sector audit director Datin Sri Shamsiah Daud (left) and deputy audit director Fadzilah Mohammad showing the 2015 Auditor-General’s Report (Series 2) at the Parliament building in Kuala Lumpur yesterday. — Bernama
Weaknesses revealed: Performanc­e sector audit director Datin Sri Shamsiah Daud (left) and deputy audit director Fadzilah Mohammad showing the 2015 Auditor-General’s Report (Series 2) at the Parliament building in Kuala Lumpur yesterday. — Bernama

Newspapers in English

Newspapers from Malaysia