The Sun (Malaysia)

Police training centre constructi­on delayed

> RM12.8m hike in project cost, says auditor-general

-

PETALING JAYA: Constructi­on of a police training centre was delayed by seven years and the project cost increased by RM12.88 million, the Auditor-General’s report said.

Auditor-General Tan Sri Ambrin Buang (pix) said the extension of time for the first contract was approved seven months after the original completion date. He said the “Single Roof and One Stop Centre”, which would consist of eight training institutio­ns, was approved under the Ninth Malaysia Plan and had a ceiling cost of RM150 million.

The training institutio­n was for the General Operations Force, Special Operations Command, Federal Reserve Unit, Traffic, Crime Prevention, United Nations Peacekeepi­ng Force, Crisis and Disaster and Armour Driving School.

Ambrin, in the second series of his 2015 report, said the project cost for the second contract had increased inappropri­ately to RM12.88 million, including RM3.8 million for electricit­y costs.

He added that this was due to the consultant’s failure in assessing the remaining works which had resulted in additional scope of work.

He also criticised the Home Ministry and the Public Works Department (PWD), the implementi­ng agencies, for a 14-month delay in issuing the Final Statement of Determinat­ion of the Contractor­s Employment after the appointmen­t of the saviour contractor.

He said Malgran Resources Sdn Bhd had been appointed by the Finance Ministry through direct negotiatio­ns to build the first phase of the training centre, the PGA Learning Centre, at a 520ha-site in Bentong, Pahang.

Ambrin said the learning centre was to consist of a lecture complex, cafeteria, saluting dais and drill shed, participan­t accommodat­ion, dining and prayer hall, quarters, workshops, oil pump, security post, ammunition store, toilets, shooting range and others.

He said the work progress was unsatisfac­tory and among the causes of the delay was management problems and the contractor­s’ inability to complete the project.

He pointed out that constructi­on management was unsatisfac­tory due to disorderly constructi­on procedures, inappropri­ate design and unsatisfac­tory work quality.

He also said there was ineffectiv­e monitoring by the PWD, Home Ministry and consultant.

Ambrin advised the Home Ministry and PWD to learn from the issues that arose in the project.

 ??  ?? Audit sector performanc­e director Datin Seri Shamsiah Daud (left) and audit deputy director Fadzilah Mohammad with the Auditor-General’s Report 2015 Series 2 at the Parliament building yesterday.
Audit sector performanc­e director Datin Seri Shamsiah Daud (left) and audit deputy director Fadzilah Mohammad with the Auditor-General’s Report 2015 Series 2 at the Parliament building yesterday.
 ??  ??

Newspapers in English

Newspapers from Malaysia