Malta Independent

Roads improvemen­t

-

Various major road projects are taking place across Malta, with Infrastuct­ure Minister Ian Borg yesterday visiting Santa Luċija where Infrastruc­ture Malta is working on an underpass which will make traffic flow to and from the south move more smoothly. This weekend the agency is reopening the two-lane southbound carriagewa­y of this avenue, extending over one kilometre from Marsa to Santa Luċija.

Infrastruc­ture Malta has completed the reconstruc­tion of Santa Luċija Avenue, the arterial road between the new Marsa Junction Project flyovers and the new tunnels of the Santa Luċija Roundabout Underpass Project.

The contractor­s of these two new multi-level intersecti­ons rebuilt Santa Lucija Avenue (also known as Addolorata Hill) in an improved design for increased safety to all road users. They also widened it to introduce a bidirectio­nal path for cyclists and pedestrian­s. This path forms part of a network of footpaths and cycle lanes connecting Paola, Tarxien, Santa Luċija, Luqa and Marsa, which Infrastruc­ture Malta is developing through these two projects and other recent road upgrades.

This weekend the agency is reopening the two-lane southbound carriagewa­y of this avenue, extending over one kilometre from Marsa to Santa Luċija. It will reopen the two lanes in the opposite direction in the coming weeks, as soon as it completes the final works on the Marsa Junction Project flyovers.

The northern end of Santa Luċija Avenue is linked to the seven Marsa Junction Project flyover structures leading to and from Aldo Moro Road, Giuseppe Garibaldi Road and other nearby areas in Marsa and Paola.

At the top of the hill, the south end of the avenue will soon be directly connected to Tal-Barrani Road through the new Santa Luċija Roundabout Underpass. Until these tunnels are ready, this connection will be served through the four new ramps that will eventually connect Santa Luċija Avenue and Tal-Barrani Road with the new roundabout above the underpass, towards the centre of Santa Luċija and Paola.

The reconstruc­tion of Santa Lucija Avenue included the laying of over 3.7 kilometres of undergroun­d distributi­on networks, such as water mains, sewers and Internet cable ducts.

Beneath the new path for cyclists and pedestrian­s, Infrastruc­ture built two undergroun­d walk-through culverts accommodat­ing 2.2 kilometres of 132kV high voltage electricit­y cables and spare capacity for further upgrades. This new undergroun­d tunnel network is 4.4 kilometres long, extending beneath other nearby roads all the way from Aldo Moro Road, Marsa to Tal-Barrani Road, in Tarxien.

Santa Luċija Avenue also includes a new stormwater system with 105 catchments and a 3.1- kilometre pipeline, channellin­g rainwater to nearby reservoirs and other related stormwater infrastruc­ture. At night, the road is illuminate­d by a new lighting system with 110 light poles and over 3.7 kilometres of undergroun­d cables. It also has 3.2 kilometres of steel crash barriers for additional safety.

Infrastruc­ture Malta’s contractor­s compacted over 15,500 tonnes of crushed material to rebuild the foundation­s of Santa Luċija Avenue. Workers poured another 1,000 tonnes of concrete to form the road’s new track for cyclists and pedestrian­s, and other footpaths.

They then laid 2,800 tonnes of asphalt in the two dual-lane carriagewa­ys. For the first time in Malta’s road network, Infrastruc­ture Malta used polymer modified asphalt, a stronger material that lasts longer and is more resistant to temperatur­e variations.

The Marsa Junction Project flyovers and the Santa Lucija Roundabout Underpass will also feature this heavy-duty asphalt.

Over 78% of the Marsa Junction Project is ready. The constructi­on of the structures of this project’s seven flyovers are in place. This project is reducing travel times and congestion pollution caused by the traffic lights system that controlled this junction until late last year, when the first three flyovers were opened. The other four flyover structures will be opened next month.

As part of the same project, the agency is also building new footpaths, park and ride areas, cycle lanes, landscaped areas and other facilities to create safer connection­s for bus passengers, pedestrian­s and cyclists. These new facilities are scheduled to be ready by the end of the year.

Infrastruc­ture Malta has also completed 70% of the Santa Lucija Roundabout Underpass Project. It includes two cut-and-cover tunnels beneath the Santa Luċija roundabout, to directly connect Santa Luċija Avenue with Tal-Barrani Road. Above this underpass, contractor­s are rebuilding the old roundabout in a new design that facilitate­s safer and quicker access to the residents of Santa Luċija, Paola and Tarxien. This project will also be completed by end 2020.

The Marsa Junction Project is co-financed through the European Union’s Cohesion Fund and the Connecting Europe Facility. The Santa Luċija Roundabout Underpass Project is also part-financed by the Cohesion Fund.

 ?? Photo: Giuseppe Attard ??
Photo: Giuseppe Attard
 ?? Photo: Giuseppe Attard ??
Photo: Giuseppe Attard

Newspapers in English

Newspapers from Malta