The Malta Independent on Sunday

Setting up of a panel of contractor­s for government work contracts

-

In a memorandum presented to one of the first meetings of the Borg Olivier government in August 1962, the Director of Public Works solicited approval to set up a panel of contractor­s who would be allowed to tender for government work contracts. The idea is to start with a panel for constructi­on work only. Later on, the panel will be extended to cover also other work such as the installati­on of electricit­y and water services, blacksmith and carpentry work, etc.

The proposal is not new. In fact, as far back as 1948 the then Minister of Works and Reconstruc­tion advanced such a suggestion and a press notice inviting applicatio­ns was issued. Unfortunat­ely, the scheme was not proceeded with possibly because it was limited to the reconstruc­tion of war damage property in ‘White Areas’.

The reasons for the setting up of a panel of contractor­s are many and varied. At present, tendering for works is completely open to anyone who cares to submit a tender. This system has only one advantage: that of securing low tender rates, possibly even cut-throat ones. Against this, there are the following grave disadvanta­ges:

It promotes excessivel­y keen competitio­n often resulting in tender rates which do not permit the workmanshi­p, and possibly also the materials, being of the required standard.

It allows competitio­n from non-bona fide contractor­s who have neither the plant nor the organisati­on to undertake the work.

It does not exclude contractor­s who have no financial backing. Such men often have to borrow money at usury rates and can only keep going by quoting cheaper and cheaper rates in order to obtain contracts.

Contracts may be secured by persons who cannot even read plans, let alone working drawings such as for complex reinforced concrete structures.

No limit is imposed on the extent of the contracts for which contractor­s may compete. Important contracts may therefore be secured by men just setting up in business.

It makes it inadvisabl­e to go out to tender for completed projects, such as the Housing Schemes, where speed would result from one contractor being responsibl­e for the whole of the work.

Under the present system, therefore, contracts are often awarded to inferior contractor­s at very cheap rates with the result that the quality of the workmanshi­p and finish is often below standard.

It may be argued that the conditions of contract provide against such inferior workmanshi­p and, if properly enforced,

“It may be stressed that the setting up of a panel would result in tender rates going up as the contractor­s ” would form rings to control prices

would safeguard against work below standard.

In theory, this is so. But in actual practice it is difficult to enforce the specificat­ions to the full when the contractor is either not equipped with men and plant to produce the standard of workmanshi­p required or has secured the contract at rates which do not allow him to do so and still make a profit.

It should be borne in mind that because of the shortage of supervisor­y staff, works of a major entity are often put up under the supervisio­n of a tradesman because a foreman is not available. Strict control at all times is therefore impossible.

It is true that the engineer could order the demolition of the parts of the structure that are not up to the required standard. But in many instances – as for example in concrete structures – it is not possible to detect defects in finish and sometimes even in workmanshi­p until long after the part has been completed.

Government is then faced with the decision of having to order the demolition of the sub-standard part and thus delay completion or of accepting inferior finish owing to pressure for early completion of the work.

It will also be argued that a contractor who is proved really unsuitable could be black-listed. Here again, this is correct in theory but quite valueless in practice. Under existing practice there is nothing to prevent a black-listed contractor from tendering under someone else’s name.

The only remedy that would eliminate the above handicaps is a panel of trusted and selected contractor­s. If this system is introduced, it may be made to resemble closely the one already obtaining in Malta in the Services Works Department, or it will work as outlined hereunder:-

Contracts for works will henceforth be classified into three value limits and contractor­s will be admitted to the panel on this basis. The panel will thus be di-

vided into three classifica­tions and each contractor will be allowed to tender only up to the limit in which he is placed.

The proposed value limits to be the following:From £1,000 to £10,000 Over £10,000 to £50,000, Over £50,000 Works below £1,000 will be open to competitio­n for all contractor­s even if outside the panel in order to allow the small contractor to continue tendering as in the past. However, this procedure would serve as a good basis to assess the small contractor’s work for his eventual inclusion in the panel.

Contractor­s will be invited to apply for inclusion in the panel by means of a Press Notice. Applicatio­ns will be accompanie­d by a Questionna­ire Form showing details of work performed, items of plant owned, number of men engaged, etc. These particular­s will first be confirmed from the reference given by each contractor. A Board will later examine the actual works performed by the contractor­s with a view to recommendi­ng

The eligibilit­y for inclusion in the panel, and

The appropriat­e classifica­tion for each contractor.

Approved classifica­tion will be revised from time to time and changes will be made on the basis of the work performed by the contractor for the government or for third parties. Contractor­s can also apply for admission to the panel or for a change of classifica­tion.

The panel will be limited to local contractor­s unless a foreign firm has a working organisati­on already in the island. This does not mean that foreign firms will be excluded from tendering, but, before considerat­ion can be given to their tenders, they will have to show that they are capable of carrying out the work satisfacto­rily. This procedure was adopted in the case of the Harbour contract.

It may be stressed that the setting up of a panel would result in tender rates going up as the contractor­s would form rings to control prices. While this is by no means certain – indeed it is improbable except for the biggest contracts for which only a few contractor­s would be allowed to tender – there can be no objection to contracts being placed at prices which permit good workmanshi­p provided these prices are below a fair estimate.

Government is expected to set a standard and to give a good example for others to follow. In this particular case, however, the private builder is far ahead of the government in that he calls for quotations only from those contractor­s who are known to be reputable and whom he can entirely trust.

Newspapers in English

Newspapers from Malta