Auckland Council caps site inspection­s

- Anne Gibson

Auckland Council has this month changed its building inspection regime by limiting the number of bookings for new developmen­ts or consents at any one time to four visits.

Jeff Fahrensohn, the council’s inspection­s manager, said that from last Wednesday developers or builders could now only book four inspection­s on their work in total at any one time, whereas before the numbers were unlimited.

“Previously, we didn’t have limitation­s and it allowed them to book as many inspection­s as they wanted which simply overloaded the system.”

Around 12 to 15 inspection­s by council officials are required for each new Auckland home including drainage, slab-down, walls-up, pre-lining, cladding, roof-on, lock-up and final inspection.

But developers and builders had been bulk-booking jobs, seeking far more inspection­s than they needed just in case their work had failed or to suit their timing, he said. So although 12 to 15 inspection­s are required all up, developers were bulkbookin­g up to 40 inspection­s per house, Fahrensohn said. “We addressed this issue because of the complaints we got from people waiting for inspection­s and due to delays growing.”

Each inspection costs $170, he said, although a cancellati­on fee of the same amount applies if the inspection is cancelled on the day it was booked for. “They just filled the whole calendar with any day they thought they might need an inspection, regardless of the load that put on us,” he said.

Those bulk bookings were made due to a variety of factors including weather conditions that could delay work, material delays, contractor­s not arriving at sites and many other reasons, he said.

“That meant they would cancel inspection­s they didn’t need at the last minute and we had up to 300 inspection­s being cancelled every single day, which created a nightmare for us, because we were unable to juggle the inspectors’ workloads each day.”

The council completes up to 1000 inspection­s a day “and if you can imagine 300 of those getting cancelled, it’s been a nightmare trying to fill those spots, because we bring people forward every day to fill those spots”.

Naveen Goel is developing a multiunit Auckland project at 78 and 80 Commodore Dr, Lynfield. He complained about the change, saying it now took longer than ever to get an inspection booking.

But Fahrensohn said Goel’s actions were precisely the ones that had resulted in changes to the system.

“This is a classic example for us,” Fahrensohn said. “He booked 66 inspection­s but cancelled 34, so more than half. When I look at that, I see 34 other builders have missed out on inspection­s. It’s just a behaviour thing. The system allowed it because there was trust built into the system.”

Fahrensohn said he could understand Goel’s frustratio­n about delays “because there’s massive pressure on everybody”.

But it was Goel’s actions and those of others like him that cost so many others, he said. Goel complained about the booking change, saying it favoured single-house developmen­t consents “and makes it exceedingl­y difficult for multi-house developmen­ts to get bookings”.

Fahrensohn said the process would bring down the waiting time for inspection­s which would make it easier for multi-unit developers to book their inspection­s when they need them.

“But it’s going to take a few weeks to pull those wait times down. We’re aiming for a wait time of only four to five days, whereas now it pretty much depends where you are. A wait time of 10 working days applies currently across the whole Auckland region with two areas slightly over that.”

Goel is developing his six-unit townhouse scheme “and under the old system, we could get inspection dates only one month ahead. This itself was causing severe delays in our project. Now, under the new system, we would virtually have to halt constructi­on until an inspection is over as we can’t book more than four inspection­s”.

The Government made a huge uproar about the housing shortage but the council keeps creating more bottleneck­s, Goel complained.

Fahrensohn said 12 new inspectors had been employed recently and were undergoing training “and more are being recruited. There are about 150 maximum inspectors but we’re down about 12 at the moment which is why we’re training them”.

 ?? Photo / Getty Images ?? Developers bulk-booking council inspection­s on all aspects of constructi­on had been clogging up the system, says Auckland Council.
Photo / Getty Images Developers bulk-booking council inspection­s on all aspects of constructi­on had been clogging up the system, says Auckland Council.

Newspapers in English

Newspapers from New Zealand