Bay of Plenty Times

Council considers appealing High Court decision

-

consent in July 2018.

In January 2019, lead project contractor Watts & Hughes Constructi­on Group Limited queried the design relating to pouring concrete floors with Harrison Grierson, which confirmed the methodolog­y.

Two months later, builders noticed a structural beam had twisted following a concrete pour and informed Harrison Grierson, which deemed the affected beam would need to be cut out and the remaining beams propped.

A wider internal investigat­ion then identified an earthquake resistance flaw and Harrison Grierson revised its drawings

The council had them reviewed by Holmes Consulting, which reported design deficienci­es in July 2019.

In September, the council ordered constructi­on to halt.

After months spent exploring remedial solutions, the council abandoned constructi­on in June 2020.

The council sold the land in April 2020 for $1 to Waibop (Harrington) Limited, a subsidiary of Watts & Hughes. The council said the land effectivel­y had no value because of the cost of demolishin­g the partly built structure.

Liability limits and insurance Retired structural engineer Arthur Park gave evidence for Harrison Grierson that if liability could not be limited, it was likely insurance premiums would rise, with this cost passed on to clients.

Barrister, mediator and arbitrator of constructi­on disputes John Walton gave evidence for the council that standard form agreements were often presented and signed as standard practice. Their liability limits reflected what the industry was prepared to pay for insurance - not by reference to the potential consequenc­es of the industry’s negligence.

Insurance brokers giving evidence for both sides generally agreed limitation of liability was a material considerat­ion for insurers.

‘Surprising’ case

Justice Tahana’s decision said alternativ­e ways of insuring against profession­al negligence were costly and had limited availabili­ty in New Zealand.

“This suggests that there is no, or a very limited, market for building owners to obtain insurance in place of engineers’ profession­al indemnity insurance.

“By agreeing to a liability cap, the non-residentia­l building owner is in effect agreeing to share the financial consequenc­es [above the value of the liability cap] if the building provider is negligent.

“I therefore do not consider that the limitation clauses agreed by TCC can be said to be in breach of the [Building Act].”

Justice Tahana also found the liability of each defendant for breach of a duty - to exercise reasonable skill and care with a view to ensuring building work complies with the building code - would be capped at the amounts specified in the contract limitation clauses.

In conclusion, Justice Tahana said it was “perhaps surprising” the issue had not previously come before the courts, given the Building Act had been around for 20 years.

There appeared to be different classes of building owners with different legislatio­n in place to protect them, Justice Tahana said.

“The consumer protection regime indicates that Parliament impliedly does not intend that non-residentia­l building owners be afforded statutory protection if they agree to limit their right to recover damages for breach the [Act].”

Kiri Gillespie is an assistant news director and a senior journalist for the Bay of Plenty Times and Rotorua Daily Post, specialisi­ng in local politics and city issues. She was a finalist for the Voyager Media Awards Regional Journalist of the Year in 2021.

 ?? Photo / Alex Cairns ?? Tauranga City Council chief executive Marty Grenfell at a council meeting.
Photo / Alex Cairns Tauranga City Council chief executive Marty Grenfell at a council meeting.

Newspapers in English

Newspapers from New Zealand