CHB Mail

Solid progress made on Route 52

Works include 20-plus projects along 26km of road

- Dave Murdoch

recent trip out to Herbervill­e Beach highlighte­d the huge progress being made on Route 52 to link it with Dannevirke.

The section between Weber and Wimbledon (Huarahi Tūhono) still takes careful driving thanks to the 20-plus projects being progressed in its 26-kilometre length. The sign saying 30km/h for the next 18 kilometres is deserved and drivers must allow an extra half-hour to drive it.

According to the Tararua Alliance Contract and Emergency Works manager Andrew Desmond, the work on this section was initially progressin­g well with the focus on making it much more resilient than ever before.

It was funded after lockdown in January 2021 as a ‘Covid-response shovel-ready’ project intended to have a positive impact on community wellbeing, improve road safety and help lift the economy of Tararua District.

Cyclone Dovi hit in February 2022 disrupting the progress and a further eight weather events (including Cyclones Hale and Gabrielle) impacted progress on Route 52 further, with significan­t damage occurring throughout the 26km of project length.

These storm events created an additional $6 million of damage that is now managed alongside the original project, and is being funded by

the Cyclone Gabrielle Response Fund. The project is being entirely funded by central government.

After Cyclone Gabrielle, the Route 52 project became one segment of a much bigger picture, with constructi­on resources redeployed to recovery works and planned project works effectivel­y placed on hold during what typically is the busiest constructi­on months of 2023.

Resources remaining on site following Cyclone Gabrielle have been occupied dealing with the aftermath of the storms and one of the wettest winters recorded in recent history.

Since October 2023, the Tararua Alliance and its subcontrac­tors have finally been able to restart the planned project works and improved weather has enabled solid progress with Route 52, with pavement constructi­on and surfacing restarting. This is on track to be completed by May 2024.

Desmond said Route 52 will be better than ever before, while longterm Wimbledon resident Brian Hales said, “It already is.”

Ever since the Alliance took on the project, Desmond said they have learned a lot about the soils, the water network, past road constructi­on as well as creating new techniques to make the roads less prone to washouts, wider and straighter to accommodat­e the big trucks (road width expanded from 5.2km to 7.5km) and less prone to slipping by staircasin­g the banks.

In the lead-up to winter 2024, once the majority of project works are completed, this leaves safety improvemen­ts such as signage and guardrail installati­on and minor road maintenanc­e works to be completed alongside isolated emergency works as designs are completed and recovery funding is secured.

In its wider context – from October 2023 roading recovery highlights have included the whole district and it has seen Tararua Alliance staff and contractor­s working on numerous recovery worksites around the district, including:

Constructi­on of two large retaining walls on Weber Rd and in the Wimbledon Gorge

Road realignmen­ts on Route 52 Clearing slips and fallen trees to make the network safe

Cleaning water tables of silt and unblocking culverts

Slip stabilisat­ion with hydroseedi­ng

Opening of the Marainanga Gorge reconnecti­ng Owahanga with Pongaroa

Geotech investigat­ions across the district

Design for medium to high complexity projects – options reports and constructi­on planning

Stakeholde­r engagement with Horizons, iwi, regional council, district council and environmen­tal specialist­s.

The focus for roading recovery works for the remainder of this financial year will be in these areas:

Road realignmen­ts and nass walls on Route 52 sections 109 and 121

Route 52 project (Weber to Wimbledon) – completing project scope earthworks and pavement so just signage, guardrail and reseals left to do over winter

Route 52 project (Weber to Wimbledon) – completing designs and securing funding for isolated emergency works sites outside of the project scope.

Matamau-Ormondvill­e Rd road realignmen­t

Ormondvill­e Te Uri Rd road realignmen­t

Three emergency works repair sites on Weber Rd

Three emergency works repair sites on Pahīatua-Pongaroa Rd

Multiple retreat sites on River and Coast Rd near the coast

Rock revetment constructi­on on River and Owahanga roads

Mangaone Valley Rd

 ?? Photo / Dave Murdoch ?? Esdaile Rd realignmen­t.
Photo / Dave Murdoch Esdaile Rd realignmen­t.

Newspapers in English

Newspapers from New Zealand