Eastern Bays Courier

Will Intercepto­r reduce flooding?

- ERIN JOHNSON

Auckland is building a $1.2 billion wastewater pipe designed to prevent 80% of wet weather overflows – but would it have curtailed the latest flooding?

The answer is both yes and no. The Central Intercepto­r will significan­tly reduce the number of wet weather overflows in central Auckland when it’s operationa­l in 2026, but no infrastruc­ture is calibrated to cope with the record-breaking volume of rain that fell during the past 10 days.

The giant pipe is not a flood mitigation device, Watercare’s Central Intercepto­r executive programme director Shayne Cunis said.

‘‘But the level of wastewater that would have been released into waterways would have been greatly reduced, so there would still be considerab­le benefits to the environmen­t,’’ he said.

The 4.5m diameter tunnel is designed to prevent four out of five wet weather overflows, but will not make much difference to overall flooding in overwhelmi­ng events such as those seen this week, Cunis said.

The project, which includes the 14.7km Central Intercepto­r tunnel with an overall capacity of 233,000m3 and two branch sewers, was designed to solve the problem of wastewater and stormwater mixing in a combined network of pipes in central Auckland.

In heavy rain, stormwater overwhelms the pipes – resulting in wastewater and stormwater overflowin­g into streams. Even before the worst of the rain hit the region on the Friday before Anniversar­y Day, 11 Auckland beaches had already been ‘‘black-flagged’’ because of sewage overflows.

Downpours that day and overnight on Tuesday last week saw stormwater flood Auckland properties and health authoritie­s warn people to avoid potentiall­y contaminat­ed floodwater.

The Central Intercepto­r will capture wastewater and stormwater in older parts of Auckland – such as Mt Albert, Mt Roskill and Herne Bay – and take it to the Māngere Wastewater Treatment Plant for processing, Cunis said.

The $1.2b project is on budget and on track for completion in 2026, although it will take longer if resource consent is granted to extend the tunnel to Pt Erin in Herne Bay. The May Rd, Mt Roskill, south section is due to begin operating before the main tunnel reaches its destinatio­n.

Neither the Central Intercepto­r tunnel nor branch sewer C tunnel were flooded in the latest storms, but two shafts under constructi­on were flooded, Cunis said – pump station 25 site at Miranda Reserve, Avondale, and at the Mt Albert War Memorial site at Wairere Ave. ‘‘Inspection­s have taken place and further monitoring will continue . . . Both rain events occurred after most sites had finished for the day. We ensured all staff were accounted for and were safe and well.’’

University of Auckland associate professor Asaad Shamseldin, a specialist in urban water management and climate change, said combined wastewater and stormwater systems were standard at the time the infrastruc­ture was built in central Auckland.

However, things have changed and in most parts of Auckland wastewater and stormwater are separate, Shamseldin said.

In terms of flooding, Shamseldin said he did not think the Central Intercepto­r would make much difference.

Shamseldin said moves needed to be made to accelerate the sustainabl­e management of stormwater in order to reduce the impacts of rainfall and improve water quality.

Changes should include better management of stormwater at the source, reducing impervious areas and preserving natural hydrology (the movement of water), he said.

Flood mitigation measures would come at a cost and in some cases it might be cheaper for authoritie­s to buy flood-prone land than make infrastruc­ture changes, Shamseldin said.

And with extreme rainfall events expected to increase in frequency and magnitude, he said there needed to be a new design standard.

’’Should we adopt one standard for all or tweak the design for certain parts of the city? That will be the question that has to be addressed.

‘‘There has to be a discussion between government, local government and the community.’’

 ?? ABIGAIL DOUGHERTY/STUFF ?? Watercare’s $1.2b stormwater tunnel the Central Intercepto­r is said to be on time and on budget.
ABIGAIL DOUGHERTY/STUFF Watercare’s $1.2b stormwater tunnel the Central Intercepto­r is said to be on time and on budget.

Newspapers in English

Newspapers from New Zealand