Hastings Leader

Pan Pac slowly up and running

After Cyclone Gabrielle wiped out their operation Pan Pac has made a slow but steady return to life

- Maddisyn Jeffares

After Cyclone Gabrielle ripped through Hawke’s Bay in February 2023, Pan Pac Forest Products’ Whirinaki site was left submerged in up to 2m-high floodwater­s and completely unrecognis­able.

Pan Pac managing director Tony Clifford said he realised they had a “marathon in front of them, not even a 10k run”.

“The water came over our stopbank system by about 750ml. The stopbanks didn’t fail, the water just came right over the top,” Clifford said.

The cyclone washed 1.8 to 2m of silt and water through the entire site, flooding the electrical systems, power distributi­on systems and control systems.

For Pan Pac, the electrical work has been the biggest repair job in both time and cost. Clifford said just for the engineerin­g cost the company is facing a repair bill of $150 million, and 12 months on it has spent close to $100m of that.

He added the $100m has largely been on plant recovery “as at this stage we haven’t started recovering any of our main administra­tion office building, which will be done in the next 18 months.”

Now, a year on from the extreme weather event that stopped Hawke’s Bay in its tracks, Pan Pac is slowly getting back to business, but with a long way to go yet.

Pan Pan had its chip mill up and running in August and September last year, and in January this year it got the sawmill running at about 50 per cent capacity. The company hasn’t been able to reactivate all of the kilns that dry the wood after it’s been through the sawmill.

More kilns are set to be up and running in a few weeks, with the hope Pan Pac will process a larger volume of wood through the sawmill.

To get to this point, Pan Pac “recognises the progress that has been done so far and the contributi­on by thousands right across Hawke’s Bay and New Zealand”, said Clifford.

As one of Hawke’s Bay’s biggest employers, Pan Pac’s recovery was aided by the creation of a list of its employees’ skill matrix and where the employees could help.

Along with finding jobs for everyone,

Pan Pac was creating job certainty as “staff were uncertain in the early stages when they came into the site and saw all the damage. We did our best to create certainty when there was mostly uncertaint­y, which helped with morale,” Clifford said.

“Once people knew they had a job and it wasn’t at risk, that created a much higher degree of comfort.”

Many Pan Pac employees come from trade background­s or had skills that were helpful to the recovery onsite.

Work in the first few months was limited to moving silt out of buildings, factories and off roads, but after that people who had specialist skills were put to work where they could best help. If staff didn’t have a particular trade skill they were still able to help

with general work or labouring. “We have had all of our operators

involved heavily with the electrical reticulati­on, none of the specialist stuff of course, just pulling out the damaged cables and pulling in the new cables, helping out in that way, while others have been helping with building, painting, gib-stopping ... you name it, our staff have helped where they can,” Clifford said.

While the Pan Pac staff have been chipping in, the managing director said that has only provided a portion of the labour required, with the vast majority of work being carried out by contractor­s.

“On a peak day of recovery in September or October there would be more than 800 people on the Pan Pac site,” Clifford said.

The managing director added, “I really can’t acknowledg­e enough the

contributi­on from our employees and contractor­s and wider stakeholde­rs.”

Pan Pac’s next major milestone is getting the pulp mill up and running, which isn’t expected to be until March and it won’t regain full capacity until November.

Clifford said that on reflection, “I want to emphasise we didn’t have any loss of life and fortunatel­y everything we have been faced with can be solved with time and money. That hasn’t been the case with other people and the things they have been facing.

“While our numbers are big and have had a significan­t impact on the business, we recognise there have been others in the community that have been impacted in other ways that have been more severe.”

 ?? Photo / Paul Taylor ?? Chris Bewick and Ryan Powell oversee the secondary operations tier while operations manager Phil Beamish White, Kerry Dash and Tony O’Keefe watch the new log in-feed via operationa­l cameras.
Photo / Paul Taylor Chris Bewick and Ryan Powell oversee the secondary operations tier while operations manager Phil Beamish White, Kerry Dash and Tony O’Keefe watch the new log in-feed via operationa­l cameras.
 ?? Photo / Paul Taylor ?? Pan Pac’s reliabilit­y engineer Aaron Harwood said everyone was excited when the first log went through the sawmill in its return to service after Cyclone Gabrielle.
Photo / Paul Taylor Pan Pac’s reliabilit­y engineer Aaron Harwood said everyone was excited when the first log went through the sawmill in its return to service after Cyclone Gabrielle.
 ?? ?? Pan Pac staff cleaning out silt from the site’s security building.
Pan Pac staff cleaning out silt from the site’s security building.
 ?? ?? The Pan Pac Whirinaki site the day after Cyclone Gabrielle.
The Pan Pac Whirinaki site the day after Cyclone Gabrielle.

Newspapers in English

Newspapers from New Zealand