Hauraki-Coromandel Post

Road design no match for extreme rain

Slip analysis reveals flaws in 1960s build

- Phil Pennington of RNZ —

Analysis of a huge slip that split a Coromandel highway shows the road design of decades ago was not up to the extreme weather of today. A huge crane and a piling rig have been trucked in to begin work on a $30 million to $40m, 125m-long steel bridge over the 110m wide slip on State Highway 25A.

An engineerin­g analysis for Waka Kotahi NZTA found the underlying soils were strong enough to prevent a deeper and larger slip occurring.

What failed at Taparahi was fill that had been tipped in to form an embankment to support the road back in the 1960s.

Cracks up to 3cm wide across both lanes on top of the embankment were spotted on January 16 this year.

Engineers tried to save the road by preventing water ponding on and seeping down into the embankment, but it did not work, the 160-page report by engineers Beca said.

“The failure appears to have been largely confined to placed fill material used to form an embankment to support SH25A. The failure of the embankment appears likely to have been associated with the extreme rainfall that occurred in the preceding months, sufficient to allow water pressures to build up within the embankment to levels greater than would have been allowed for when the embankment was constructe­d in the 1960s.”

January had seven times more rain than normal near the slip, or 1400mm, though at no point was the rain especially intense.

Investigat­ions after the slip, which occurred in two phases, on January 28 and February 1, located the original ground surface in many spots, “indicating that the in situ soils had sufficient strength to prevent a deeper and larger failure from occurring”.

The land around the slip had been fairly stable since the slip.

“Recent wet weather did not trigger instabilit­y in the steep natural slopes above the failed embankment or in the in situ materials supporting the embankment.”

The engineers looked into but had found no way of temporaril­y reinstatin­g the road while the permanent repair was being done, it said.

The report detailed five fix options, of which Waka Kotahi chose the second cheapest and fastest, a steel bridge with a precast concrete deck.

This was costed at between $23 million and $28m and forecast to take 11 to 13 months to build.

The agency has promised to build it faster, by next March. It expected to get a building consent exemption from Thames Coromandel District Council, the July 17 report said.

Though engineers agreed liquefacti­on was unlikely, nonetheles­s, any new build had to cope with “poor” conditions and “marginal slope stability” at the slip site itself.

“All remediatio­n options developed have considered slope stability and include stabilisat­ion measures to meet required design standards. Care will be needed during remediatio­n to avoid undercutti­ng at the base of these slopes” above the slip. Realigning the whole section was ruled out, by cost (up to $54m) and time (up to three years), wildlife laws and soil disposal needs.

To the north was land managed by the Department of Conservati­on, and to the south Ma¯ori freehold land, which would have taken several months to try to acquire, with no guarantee whether areas needed alignment shifts or other roadworks.

An embankment or a retaining option posed greater risks around ground conditions than a bridge.

The bridge would have long spans of 25-37m to cut down on how many piers were needed, “and thus reduce safety and constructi­on risk”.

The bridge’s 15 big steel beams were being made in Hawke’s Bay. “The team there are working around the clock,” NZTA said.

 ?? ??
 ?? Photo / Waka Kotahi Photo / Philip Hart ?? State Highway 25A on the Coromandel was washed out near the summit.
Engineers have blamed the huge SH25A slip on fill used to create an embankment on the Kopu-hikuwai Rd in the 1960s.
Photo / Waka Kotahi Photo / Philip Hart State Highway 25A on the Coromandel was washed out near the summit. Engineers have blamed the huge SH25A slip on fill used to create an embankment on the Kopu-hikuwai Rd in the 1960s.

Newspapers in English

Newspapers from New Zealand