Hauraki-Coromandel Post

Piling work complete on new SH25A bridge: NZTA

Significan­t progress made since work began in late June

-

Waka Kotahi has given an update on constructi­on of the State Highway 25A Kopu-hikuai bridge at Taparahi that includes the news that piling has now been completed.

The progress made on the site has been significan­t since the rebuild began in late June.

In a release, Waka Kotahi said there are still some uncertaint­ies in the building programme because of “variables in constructi­on”. These include fabricatio­n of the beams, deck constructi­on and impacts from the wind on crane lifts.

“We’re working really closely with our contractor to accelerate delivery. The contractor is currently delivering to the proposed programme and last week finished the piling,” the statement read.

“We know how much it means to the Coromandel to reopen this road and we’re committed to building this bridge in the shortest time possible.

“Last week our piling crew finished the bridge piling.

“Both the crew and rig are off to another project. They were a dedicated team who worked in both challengin­g and difficult conditions.

“Other activity nearing completion is the earthworks and slip stabilisat­ion.

“This is a great achievemen­t, especially after working in muddy and challengin­g conditions for the first two months of the project.

“Above the ground, bridge constructi­on continues, and the team has made great progress this past week.” The progress was outlined: Abutment A + D: Completed the first two pours at Abutment A (the main beam and the plinth). At Abutment D the steel fixing for the main beam has been completed.

■ Pier B: Finished installing the steel casing and reinforcem­ent for the last two columns and poured all four. These columns will support the bridge deck. You’ll see in the photos a platform the team built up at site and then later lifted on top of the columns — this is so they can safely access and pour the columns and construct the headstocks.

■ Pier C: All four piles were drilled and poured — it’s the last set for the new bridge.

These piles have been cropped and the team will start placing the steel columns and temporary works for a concrete pour planned later this week.

■ Off site: The first set of steel bridge girders have been coated and are ready to leave Napier. The bridge girders are due to be delivered to the site in early October. This set of girders will be lifted and placed between Abutment A and Pier B, forming the base of the bridge deck.

The bridge’s girders, which are being manufactur­ed off site in Napier, are ready for dispatch, Waka Kotahi said.

“The team in Napier continue to work around the clock with the first set of steel bridge girders ready for their journey to Taparahi.”

 ?? Image / Waka Kotahi ?? Giant piles were driven down more than 20m to support the new viaduct bridge at SH25A’S Taparahi site.
Image / Waka Kotahi Giant piles were driven down more than 20m to support the new viaduct bridge at SH25A’S Taparahi site.
 ?? Photo / Waka Kotahi ?? The piling on the site has been completed.
Photo / Waka Kotahi The piling on the site has been completed.

Newspapers in English

Newspapers from New Zealand