Hauraki-Coromandel Post

Tapu-coroglen reopening on track

Work on vital road expected to be finished soon

- Jim Birchall

The contractor responsibl­e for repairs to three sites on the vital trans-peninsula route Tapu-coroglen Rd says the completion of the rebuild of the storm-ravaged road is imminent.

The road was severely damaged by last summer’s weather events and has remained closed 10 kilometres from the settlement of Tapu.

Geotechnic­al investigat­ions in June revealed that a large slip had formed on the slope above the road at the same site. An initial plan to widen the width of the road to one lane of traffic and open by June never materialis­ed as a retaining wall to protect the road from the unstable slope above needed to be built concurrent­ly with a retaining wall built from the river below to support the road.

In March, Labour leader Chris Hipkins visited Tapu-coroglen Rd to assess the storm-ravaged region’s infrastruc­ture first-hand, concluding; “We know we have a big job ahead of us.”

Delays caused by Cyclone Lola at the back end of October, and site vandalism, initially affected the speed of the project, but in a release, Thames Coromandel District Council (TCDC) said that “time has been made up” by Coromandel-based contractor­s Kelsey Constructi­on.

“[Weather dependent] we anticipate having the route open by Friday 8 December, earlier than originally expected,” said TCDC.

Earlier this year, Kelsey Constructi­on worked to reopen roads in Colville, Port Jackson and other stormimpac­ted regions.

TCDC said, “The design chosen uses mass block retaining walls to support the underslip, with materials sourced from local suppliers. This method has been chosen to ensure works can be completed quickly while providing a long-term solution that meets long-term needs.

“Works for the three sites on Tapucorogl­en Rd have been packaged together to maximise efficiency.”

The company planned to have the road reopened in mid-december, weather-dependent.

Repair works to fix three sites and reinstate the slip-damaged Kennedy Bay Rd began on Monday, November 27. Nicholls and Uttinger Civil Ltd will be undertakin­g the work.

The site locations and estimated programme for the works are below (in order of constructi­on).

All distances are measured from the start of Kennedy Bay Rd, which starts from the end of Driving Creek Rd:

Site 2: 3.4km, Constructi­on period: 4/12/23 to 8/12/23

Site 3: 1.1km, Constructi­on period: 11/12/23 to 15/12/23

Traffic management will be in place for the three sites, including speed restrictio­ns and traffic lights. You can expect up to 15-minute delays during work hours (7am to 7pm Monday-saturday).

 ?? Photo / Jim Birchall ?? Then Prime Minister Chris Hipkins inspects road damage on the Tapucorogl­en Rd on March 9.
Photo / Jim Birchall Then Prime Minister Chris Hipkins inspects road damage on the Tapucorogl­en Rd on March 9.
 ?? ?? A slip in January on the Tapu-coroglen Rd.
A slip in January on the Tapu-coroglen Rd.

Newspapers in English

Newspapers from New Zealand