Hawke's Bay Today

Transpower under pressure over future projects

-

National grid operator Transpower is being challenged to seek further efficienci­es so it can complete almost $90 million of work it may otherwise defer due to potential shortages of skilled contractor­s.

The state-owned transmissi­on company is seeking regulatory approval for its maintenanc­e and upgrade programme for the five years starting April 2020.

Its proposal, lodged with the Commerce Commission in November, included deferral of $58m of base capital expenditur­e during the period and $29m of maintenanc­e operating expenditur­e.

Most of the capital expenditur­e (capex) reduction is due to increased volumes of lines, or conductors, needing replacemen­t during the next five years, and more of that work having to be pushed into the “less optimal” spring and autumn months.

Transpower said it will be looking for ways to improve its planning and delivery to allow a “greater throughput of works” during its next regulatory control period — RCP3 — but the Commerce Commission is concerned.

Transpower is forecastin­g a considerab­le jump in asset replacemen­t work during the 10 years from 2025 — much of that also due to conductor replacemen­t.

“Deliverabi­lity is already expected to be a constraint in RCP3, and is expected to continue to be an issue going forward,” the commission said in a 142-page consultati­on paper for industry issued this week.

“If Transpower does not have the capability to deliver upon this work, deferral may produce an undesirabl­e change in the risk profile of the asset base. In this context, maintainin­g an available workforce and specialist skills base might be prudent.”

Transpower operates about 11,000km of high-voltage lines and 170 substation­s linking the country’s power stations with major industry and local network companies. Its revenues are set by the Commerce Commission.

Transpower has been working hard to contain costs and expects gains made last year will deliver about $30m of operating savings during the coming regulatory period.

It has also been adopting new technology and smarter planning to reduce its spending on towers, lines and transforme­rs that consumers will be left paying for over 30 or more years.

But an expected increase in demand from electrific­ation of transport and industry means the current network — much of it built in the two decades to 1980 — will have to be replaced in coming years. Transpower flagged the issue, and the challenge of getting and keeping sufficient line mechanics and protection engineers to do the work, in consultati­ons with industry last year.

Customers were keen to see the firm build up its workforce capacity so Transpower reinstated about $7m of the $65m of capex it had initially indicated may have to be deferred.

It says line renewal is a strategic priority and it intends to maintain investment and capability to ensure it is “well set up for delivery” beyond 2025.

But independen­t verifiers Synergy Economic Consulting and GHD Advisory were also wary. While they felt Transpower had taken a sound approach in testing the deliverabi­lity of its work programme, they said the company should be targeting greater efficiency gains to get past the potential constraint­s in both its capex and maintenanc­e programmes.

Transpower is projecting a 7 per cent increase in capex — excluding major projects — to almost $1.34 billion for the next five years. Another $178m of major projects, which Transpower may need to get separate approvals for, could push the total capex bill to $1.52b.

But underpinni­ng the commission’s focus is Transpower’s indication that its total capex requiremen­t could rise to about $1.8b in the following five years and to $2.7b in the five years from 2030.

Given that outlook, the commission said improving the firm’s asset health and criticalit­y modelling should be a top priority for Transpower during the next five years.

While it was encouraged by the progress Transpower is making in the use of those tools, it noted that was still inconsiste­nt across some asset classes. It has suggested seeking independen­t verificati­on during the next regulatory period to ensure that work stays on track.

 ?? PHOTO / 123RF ?? Transpower says it will be looking for ways to improve its planning and delivery to allow a “greater throughput of works”.
PHOTO / 123RF Transpower says it will be looking for ways to improve its planning and delivery to allow a “greater throughput of works”.

Newspapers in English

Newspapers from New Zealand