Kapiti News

Motorway to open by Christmas

-

Wellington’s Transmissi­on Gully motorway is scheduled to open before Christmas 2020, the NZ Transport Agency said.

The agency has also provided additional financial relief for the motorway’s makers because of a number of issues experience­d during the constructi­on.

NZ Transport Agency interim CEO Mark Ratcliffe said the financial settlement with the joint venture builder CPB HEB JV will ensure the gully route is completed to a high standard, meets the needs of customers and still achieves good value for money for New Zealanders.

“Transmissi­on Gully is a highly complex project being built on 27km of very difficult terrain.

“Progress has been slower than anticipate­d due to a number of issues encountere­d during constructi­on including the Kaikoura earthquake in 2016 which diverted resources and materials. Constructi­on has been impacted by the challengin­g conditions of the site.

“The project has required an increased earthworks programme, creating further complexity, disruption and cost to the project through the additional consent requiremen­ts.

“These issues, and the impact from several storm events and the Kaikoura Earthquake, have meant CPB HEB JV has incurred significan­t additional costs to construct the project.

“In acknowledg­ement that these issues were out of the control of CPB HEB JV and not something they could have reasonably anticipate­d the Transport Agency has provided $190.6m of financial relief to CPB HEB JV.

“The majority of the money will go towards supporting CPB HEB JV, local sub-contractor­s and employment while also ensuring the Transport Agency still achieves good value for money for Transmissi­on Gully,” he said.

The settlement is conditiona­l on the PPP contractor, Wellington Gateway Partnershi­p, becoming a party to the settlement.

“The parties are working through satisfying the conditions and obtaining the necessary approvals.

“As part of the settlement, CPB HEB JV’s historic claims against WGP and the Transport Agency have been resolved without resorting to court action which would have resulted in further costs and delays to the project.

“As with all projects’ timeframes and expected completion dates, we are always dependent on good weather.

“CPB HEB JV will be working very hard to complete the motorway by Christmas, subject to good progress through the next six to nine months and to passing a series of standard quality safety and environmen­tal checks prior to opening.”

Mr Ratcliffe said once open, there will be further work required before the project is fully completed, including landscapin­g and testing and commission­ing of new technology systems.

“These works will most likely be completed by mid-2021.

“The Transport Agency, WGP and CPB HEB JV are committed to working together to complete the project and we remain excited about the opening of Transmissi­on Gully and the many benefits that it will bring for our customers, Wellington and the central and lower North Island.”

The money for the settlement has come from the National Land Transport Fund and will not impact any other projects currently being progressed on the State Highway network.

It is not related to the Government’s $6.8b NZ Upgrade Package that was announced in January.

Transmissi­on Gully key facts

* Transmissi­on Gully is a four-lane, 27km motorway running from Mackays Crossing at Paeka¯ ka¯ riki to Linden.

* Four interchang­es and two link roads will connect the motorway to Mackays Crossing, SH58, eastern Porirua and Kenepuru.

* It includes over 10.2 million cubic metres of earth moved, and cuts of up to 70 metres.

* There will be 25 structures (bridges and major culverts) equating to a total length of more than one kilometre; the largest structure is the bridge over Cannons Creek — 230 metres long and 60 metres high.

* More than 534ha of ecological mitigation areas and 27km of stream remediatio­n, restoring native landscapes and mitigating the sedimentat­ion effects of the project on waterways.

 ?? PHOTO / ROSALIE WILLIS ?? Transmissi­on Gully’s Wainui Saddle.
PHOTO / ROSALIE WILLIS Transmissi­on Gully’s Wainui Saddle.

Newspapers in English

Newspapers from New Zealand