Kapiti News

Not sealed and not signed till it’s safe

Transmissi­on Gully far from ready for 25,000 daily drivers

- Georgina Campbell

No one should be surprised that Transmissi­on Gully, the new 27km motorway out of Wellington, is being ripped up for repairs when it hasn’t even opened.

After all, the four-lane-highway has been plagued by flawed chipseal and water seeping through the road’s surface.

The NZ Herald revealed these problems in December after independen­t inspection reports were released under the Official Informatio­n Act.

Yet, despite this informatio­n about the known defects being well publicised, a leaked letter has been circulatin­g, leading some to claim the road is ready to open.

If only one letter was enough to schedule a ribbon-cutting ceremony.

Transmissi­on Gully is being built through a public-private partnershi­p (PPP), the Wellington Gateway Partnershi­p (WGP), with CPB Contractor­s and HEB Constructi­on subcontrac­ted to carry out the design and constructi­on.

The letter was from expert transport engineer Jon England, dated December 10, which said he had inspected the road.

“It is my profession­al opinion that the Transmissi­on Gully main alignment and lighting is in good and efficient repair, and may safely and convenient­ly be used for public traffic,” the letter said.

Waka Kotahi NZTA said the letter was a safety report required under the Government Roading Powers Act.

The inspection involves driving over the alignment to make sure there is nothing obviously unsafe. Its scope does not include things like checking the median barriers have been installed at the right height or certificat­ion of retaining walls and bridges.

It also doesn’t include making sure any outstandin­g constructi­on defects are rectified.

That’s why there are 100 safety and quality assurance tests required for the road to open and the letter is just one test which needs to be satisfied.

So the letter really cannot be considered in isolation if one wants to reach a conclusion as to whether the road is fit to be open.

Especially considerin­g the pavement defects have now been dug up, meaning a new safety report will likely be required anyway.

Last week Waka Kotahi released photos of the repairs, presumably to dispel claims the road is fit to open.

One photo shows rollers doing remedial work to address the bleeding of the chipseal surface.

Another one shows milling and repair work underway north of the Waitangiru­a Interchang­e.

A third photo shows the road being dug up to install a subsoil drain to manage water issues.

Waka Kotahi transport services general manager Brett Gliddon said several issues remained with both the asphalt and chipseal surfaces which required remedial work.

“Waka Kotahi can confirm that the issues are serious enough to have not yet met the safety and quality assurance tests relating to pavements and surfacing requiremen­ts for road opening.”

Waka Kotahi has not yet received an opening date, or a timeframe to complete the work required to open the road, from WGP or CPB HEB,

Gliddon said. There is now immense public pressure to get the road open as soon as possible.

Last Wednesday the region’s Chambers of Commerce issued a press release calling for an independen­t inquiry, despite the fact a review undertaken by Te Waihanga (the Infrastruc­ture Commission) is already in play.

Preliminar­y findings of the review found serious flaws at the planning stage of the project, underminin­g the successful completion of the fourlane motorway.

“There have also been other issues and cost overruns during Transmissi­on Gully’s constructi­on and Wellington­ians deserve answers,” Infrastruc­ture Minister Grant Robertson said at the time the findings were released.

Te Waihanga has been directed to undertake a further review of the project after constructi­on has been completed.

The road is clearly not currently fit to be open.

The last thing anyone wants is for it to open prematurel­y and then close again because it’s falling to pieces.

Or, even worse, taxpayers being on the hook for those costs.

While “contractua­lly agreed safety and quality assurance tests” might sound boring, it’s important they are airtight when the road is handed over to Ventia, who will operate and maintain the motorway for 25 years after its built.

If those standards are not met, it’s ultimately the taxpayer who will be pouring even more money into Transmissi­on Gully, which has already been the subject of several budget blowouts.

These tests and the resource consents needed for the road to open might feel like government bureaucrac­y getting in the way of the road opening, but some of them are as tangible as the chipseal that 25,000 vehicles a day will eventually be driving on.

 ?? Photo / Waka Kotahi New Zealand Transport Agency ?? Parts of the Transmissi­on Gully road have been ripped up for repairs after problems were identified with the road surface.
Photo / Waka Kotahi New Zealand Transport Agency Parts of the Transmissi­on Gully road have been ripped up for repairs after problems were identified with the road surface.

Newspapers in English

Newspapers from New Zealand