Kapiti News

Steady progress on bridge clip-on

Frustratio­n grows over detour caused by the project

- David Haxton

We understand that this changes people’s daily routines and can be frustratin­g. . .the one-way detour is the best approach, considerin­g traffic flow and safety. Infrastruc­ture delivery regional manager Jetesh Bhula

Good progress is being made to attach a shared path to the Waikanae River bridge on old State Highway 1, on the Kāpiti Coast, as motorists grapple with detours and queues.

The clip-on shared path is being constructe­d to make it safer for pedestrian­s and cyclists crossing the bridge.

But constructi­on has meant two lanes have been reduced to a single lane for northbound traffic, while southbound traffic has to detour via an expressway.

The detour has seen traffic queued along Te Moana Rd as well as backed up past the Paraparaum­u off-ramp which has been a hot topic of conversati­on on social media.

Adding further to the frustratio­n has been the project’s timeframe with completion expected in May or June.

“We know the traffic changes for this work mean longer journeys for many people and that there is extra traffic on the detour route,” infrastruc­ture delivery regional manager Jetesh Bhula said.

“We understand that this changes people’s daily routines and can be frustratin­g. We have considered the alternativ­es, including a stop/go on the bridge.

“The one-way detour is the best approach, considerin­g traffic flow and safety. The traffic management plan was signed off by both NZTA/ Waka Kotahi and Kā piti Coast District

Council (KCDC) traffic management co-ordinators, who are trained to assess traffic management plans and have knowledge of the local network. Experience of previous stop/go in the area showed that this resulted in long queues, delays, and safety issues.”

Bhula said the agency’s Wellington Transport Operations Centre (WTOC) was actively monitoring the detour route and adjusting the traffic lights’ phasing to minimise queues as much as

possible.

“We are working hard to reduce the queues by constantly making changes in response to traffic flows. The WTOC team also manage electronic signage on the expressway to alert drivers if there are queues.”

Bhula said the project, still projected to cost $1.9 million, was “progressin­g well”.

“The first steps in the project include building foundation­s for the new walking and cycling path at both ends of the bridge. Over the last two weeks, we have dug out the foundation sites and poured the first concrete. We have also removed the bridge’s old side barrier and added a temporary railing in its place.

“We are currently building a platform for the 220-tonne crane that crews will use to lift the customdesi­gned, prefabrica­ted path sections on to the bridge. The five sections that will span the river have been assembled at our contractor­s’ yard in Otaihanga. As oversize loads, they’ll be carefully transporte­d to the site, one by one, once the foundation­s are complete. We will then attach each one, in turn, securely to the bridge brackets.”

The prefabrica­ted bridge trusses were specifical­ly designed and built for the Waikanae River bridge.

“Earlier in the project, some alteration­s were made after issues with an initial design. This is not delaying the current constructi­on work. The contractor­s were required to do this within the existing contract price at no extra cost to NZTA/Waka Kotahi and KCDC. There are now no issues with the trusses.”

The project was still expected to run until May/June.

“We are working with our contractor­s to identify opportunit­ies to accelerate the work, as we understand the detour is disruptive. We will keep the community updated if project timeframes change.”

 ?? Photo / Mark Tantrum ?? The five individual sections that will span the river have been assembled.
Photo / Mark Tantrum The five individual sections that will span the river have been assembled.

Newspapers in English

Newspapers from New Zealand