Manawatu Guardian

Big win for contractor Fulton Hogan

Signs maintenanc­e contract with Manawatu¯ District Council This contract represents the largest single budget area within the overall council work programme, which covers roading repairs and maintenanc­e, road sealing, footpath repairs, drainage works and

- Judith Lacy

Manawatu¯ District Council has selected Fulton Hogan as its road maintenanc­e contractor for the next three years. The contract will start on July 1. Infrastruc­ture manager Hamish Waugh said there was a high level of interest in the contract from New Zealand’s largest infrastruc­ture contractor­s.

Fulton Hogan was selected as the preferred contractor based on several attributes, including proficienc­y and pricing, he said.

“We were really impressed with the high calibre of tender applicatio­ns received, ensuring this has been a robust and thorough selection process.”

The three-year contract is worth about $38 million, subject to final NZ Transport Agency confirmati­on of the 2024-27 road maintenanc­e funding envelope.

“This contract represents the largest single budget area within the overall council work programme, which covers roading repairs and maintenanc­e, road sealing, footpath repairs, drainage works and attendance to emergency and weather events.”

Fulton Hogan has committed to working with several establishe­d infrastruc­ture suppliers in Manawatu¯ , ensuring the local contractin­g market is supported.

“This local knowledge will ensure the roading network is looked after to the highest possible standard within our available budgets,” Waugh said.

The contract has two rights of renewal of three years each, upon satisfacto­ry performanc­e and subject to council agreement.

Fulton Hogan replaces Higgins, which held the Manawatu¯ District Council road maintenanc­e contract for nine years.

In 2021, Fulton Hogan replaced Higgins as Palmerston North City Council’s road maintenanc­e contractor.

A March 2021 officer report recommendi­ng elected members approve the awarding of the contract to Fulton Hogan said the company provided the highest-quality tender and the lowest price.

Three tenders were received, but the names of the other two companies were redacted. The Palmerston North contract is for three years and is worth $38 million.

In August 2022, elected members asked for an external review of the contract to identify challenges causing the deteriorat­ion of the city’s road network.

The review was done by Building Intelligen­ce Group, which said it was common for contracts to be reviewed at this stage.

Building Intelligen­ce Group recommende­d retaining the contract with Fulton Hogan. It acknowledg­ed there were some aspects of the contract that worked well and some that needed rescoping. The review highlighte­d ways in which council staff and Fulton Hogan could work more collaborat­ively.

The council’s summary of the report says it is committed to working with Fulton Hogan. Mayor Grant Smith, chief executive Waid Crockett and chief infrastruc­ture officer Chris Dyhrberg met with national and regional Fulton Hogan leadership to discuss the review.

The review noted staff turnover at the council when the contract moved from Higgins to Fulton Hogan led to a lack of continuity. Fulton Hogan struggled initially to resource the contract due to the pandemic as well as workforce shortages.

The review found the present approach to managing the city’s roads was reactive, with complaints from the public driving the work programme.

This work does not fix the underlying issues causing the failure of road surfaces.

There have been budget shortfalls. For example, emergency work caused by extreme weather events is funded through existing budgets, which are already stretched by contract inflation fluctuatio­ns.

Contract inflation fluctuatio­ns are changes in the overall cost of goods and services that affect the cost of maintainin­g and repairing roads. They could include the cost of materials, labour and fuel.

These fluctuatio­ns are also unfunded and now exceed 20 per cent of the total value of the contract. The impact is a reduction in the available budget to renew and maintain the road network.

The review found the general condition of roads in Palmerston North met the applicable standards set by NZTA and that the council is performing better than other councils on most classes of road.

The review was discussed in a public-excluded council meeting in September.

The accompanyi­ng officer report will not be released until the conclusion of the negotiatio­ns with Fulton Hogan for a renewed term of the contract.

Fulton Hogan was founded in Dunedin in 1933 by Jules Fulton and Bob Hogan.

Meanwhile, Higgins has been awarded the contract to construct the section of the Feathersto­n St cycleway and pedestrian improvemen­ts between Aroha St and North St.

It will install raised pedestrian crossings outside Central Normal School and Palmerston North Boys’ High School, a separated unidirecti­onal cycleway on both sides of the road, and changes to the lane layout and light phasing at the Rangit¯ıkei St intersecti­on.

In 2016, Higgins was purchased by Fletcher Building and is now part of the Fletcher Constructi­on family of brands.

 ?? Photos / Judith Lacy ?? Fulton Hogan’s new Manawatu¯ depot on the corner of Richardson­s Line and Setters Line, on the outskirts of Palmerston North. It has moved from Kaimanawa St in Kelvin Grove.
Photos / Judith Lacy Fulton Hogan’s new Manawatu¯ depot on the corner of Richardson­s Line and Setters Line, on the outskirts of Palmerston North. It has moved from Kaimanawa St in Kelvin Grove.
 ?? ?? Fulton Hogan is repairing the road surface opposite the Lido Aquatic Centre in Park Rd, Palmerston North.
Fulton Hogan is repairing the road surface opposite the Lido Aquatic Centre in Park Rd, Palmerston North.

Newspapers in English

Newspapers from New Zealand